The Wellsburg Bridge project Finding of No Significant Impact (FONSI) and other documents are available at http://www.transportation.wv.gov/highways/engineering/comment/wellsburgbridge/Pages/default.aspx.
May 2008 — Notice to Proceed given to ConsultantOctober 2008 — Information Workshop Public MeetingsWelcomeRecommended Priorities from the 2003 StudyStudy Area MapTimelineJune 2009 — Submit Design Study Field Review PlansAugust 2009 — Public Meetings to present Alternatives and Environmental ConstraintsOctober 2009 — Submit Design Study Office Review PlansJanuary 2010 — Submit Draft Design ReportMarch 2010 — Environmental Assessment available for circulationApril 2010 — Public MeetingsSeptember 2010 — Conclusion of Environmental Assessment (Finding of No Significant Impact Approval)October 2010 — Submit Final Design Report for Initial Design StudiesFebruary 2011 — Location & Design ApprovedMarch 2011 and Beyond — Begin Phase II (Preliminary and Final Design)