Major Submissions
- May 2008 — Notice to Proceed given to Consultant
- October 2008 — Information Workshop Public Meetings
- June 2009 — Submit Design Study Field Review Plans
- August 2009 — Public Meetings to present Alternatives and Environmental Constraints
- October 2009 — Submit Design Study Office Review Plans
- January 2010 — Submit Draft Design Report
- March 2010 — Environmental Assessment available for circulation
- April 2010 — Public Meetings
- September 2010 — Conclusion of Environmental Assessment (Finding of No Significant Impact Approval)
- October 2010 — Submit Final Design Report for Initial Design Studies
- February 2011 — Location & Design Approved
- March 2011 and Beyond — Begin Phase II (Preliminary and Final Design)
|