West Virginia Department Of Transportation
Division of Highways
Bid Results - Letting of June 10, 1997
CALL | PROJECT NUMBER & BIDDERS | COUNTY | BID | DBE |
001 | S320-4/1-7.26-02 | KANAWHA | ||
Joseph B. Fay | 114,300.00 | |||
Orders Construction Company | 117,252.50 | |||
Alan Stone Co. | 136,875.00 | |||
002 | ER-0196(034)E E315-2-D04.82 | HANCOCK | ||
Ohio-West Virginia Excavating Co. | 34,226.25 | |||
James White Construction Co. | 36,985.00 | |||
003 | NH-0050(120)E S317-50-3.37 | HARRISON | 5.00 | |
MEC Construction Inc. | 271,000.00 | 100.00 | ||
Ahern & Associates Inc. | 273,500.00 | 5.00 | ||
Bilco Construction Company Inc. | 283,078.00 | 5.00 | ||
Becdir Construction Company | 293,088.00 | 5.00 | ||
The Velotta Company | 303,367.00 | 5.00 | ||
Upon This Rock Construction | 397,000.00 | 5.00 | ||
004 | E399-DEM/OL-G09.96 FEMA 1137 | VARIOUS | ||
Enviroserve Inc. | 398,500.00 | |||
Auto Mart Inc. | 417,000.00 | |||
R..H. Armstrong Inc. | 479,800.00 | |||
005 | S309-19-6.66 | DODDRIDGE | ||
SMH Construction Co., Inc. | 259,121.58 | |||
Bilco Construction Co. | 285,583.00 | |||
Teays River Construction | 290,230.00 | |||
MEC Construction | 321,252.75 | |||
M & H Concrete Structures Inc. | 322,817.30 | |||
Orders Construction Co., Inc. | 350,630.29 | |||
Turman Construction Co. | 375,771.75 | |||
Alan Stone Co., Inc. | 394,818.34 | |||
Upon This Rock Construction | 397,000.00 | |||
006 | S338-219-34.78 | POCAHONTAS | ||
SMH Construction Co., Inc. | 479,651.15 | |||
Bilco Construction Company | 584,590.00 | |||
Fayette Construction Company Inc. | 591,253.70 | |||
Teays River Construction | 629,705.00 | |||
M & H Concrete Structures Inc. | 635,042.60 | |||
Orders Construction Company Inc. | 676,106.38 | |||
007 | S331-19-11.08 | MONONGALIA | ||
Bilco Construction Company | 104,227.00 | |||
Upon This Rock Construction Inc. | 147,000.00 | |||
Ahern & Associates Inc. | 160,000.00 | |||
Orders Construction Company Inc. | 165,603.60 | |||
008 | S343-31/4-4.15 | RITCHIE | ||
Manganas Painting Co. | 147,533.50 | |||
Specialty Groups Inc. | 174,219.25 | |||
Monoko Inc. | 177,426.00 | |||
W.R. Mollohan | 196,040.75 | |||
Damalos & Sons Inc. | IRREGULAR | |||
009 | S306-9-2.19 | CABELL | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 24,424.15 | |||
West Virginia Paving Inc. | 27,430.80 | |||
Orders & Haynes Paving Co., Inc. | 29,593.50 | |||
010 | S306-10-13.79 | CABELL | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 47,952.52 | |||
West Virginia Paving Inc. | 51,749.25 | |||
011 | S306-16-2.05 | CABELL | ||
Orders & Haynes Paving Co., Inc. | 51,036.85 | |||
West Virginia Paving Inc. | 53,100.90 | |||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 53,726.05 | |||
012 | S306-52/3-0.28-01 | CABELL | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 102,635.99 | |||
West Virginia Paving Inc. | 130,455.95 | |||
013 | S306-66-2.02 | CABELL | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 40,424.20 | |||
West Virginia Paving Inc. | 43,484.30 | |||
014 | S308-5-7.60 | CLAY | ||
West Virginia Paving Inc. | 97,433.83 | |||
Orders & Haynes Paving Co., Inc. | 100,880.52 | |||
Meadows Stone & Paving | 137,038.00 | |||
015 | S310-5/2-0.00 | FAYETTE | ||
West Virginia Paving Inc. | 93,994.80 | |||
016 | S310-9-0.00 | FAYETTE | ||
West Virginia Paving Inc. | 103,011.84 | |||
017 | S310-19/6-0.00 | FAYETTE | ||
West Virginia Paving Inc. | 15,896.80 | |||
018 | S310-21/20-0.00 | FAYETTE | ||
West Virginia Paving Inc. | 119,171.16 | |||
019 | S310-22-3.30 | FAYETTE | ||
West Virginia Paving Inc. | 80,944.30 | |||
020 | S310-41-26.82 | FAYETTE | ||
West Virginia Paving Inc. | 170,216.64 | |||
021 | S310-60-8.89 | FAYETTE | ||
Orders & Haynes Paving Co., Inc. | 58,682.80 | |||
West Virginia Paving Inc. | 78,648.97 | |||
022 | S310-60-17.48 | FAYETTE | ||
West Virginia Paving Inc. | 247,481.90 | |||
Orders & Haynes Paving Co., Inc. | 260,605.15 | |||
023 | S313-9-2.95 | GREENBRIER | ||
West Virginia Paving Inc. | 100,989.14 | |||
024 | S313-9-14.81 | GREENBRIER | ||
West Virginia Paving Inc. | 34,142.33 | |||
Waco Oil & Gas Co. | 38,679.50 | |||
025 | S313-23-0.00 | GREENBRIER | ||
Waco Oil & Gas Co. | 86,724.08 | |||
West Virginia Paving Inc. | 86,776.88 | |||
026 | S313-33-0.00 | GREENBRIER | ||
West Virginia Paving Inc. | 63,557.00 | |||
027 | S317-1-0.00 | HARRISON | ||
Mountaineer Contractors Inc. | 86,688.45 | |||
J.F. Allen Company | 89,082.00 | |||
Dodd General Contractors | 93,874.12 | |||
Ohio Valley Paving Corp. | 94,229.57 | |||
028 | S317-2-1.98 | HARRISON | ||
Mountaineer Contractors Inc. | 34,188.12 | |||
J.F. Allen Company | 35,023.20 | |||
Ohio Valley Paving Corp. | 35,582.92 | |||
Dodd General Contractors | 41,069.79 | |||
029 | S317-5/6-0.00 | HARRISON | ||
Dodd General Contractors | 66,499.05 | |||
Ohio Valley Paving Corp. | 70,099.40 | |||
Mountaineer Contractors Inc. | 70,995.54 | |||
J.F. Allen Company | 72,418.60 | |||
030 | S322-2-0.00 | LINCOLN | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 50,546.50 | |||
Orders & Haynes Paving Co., Inc. | 52,054.60 | |||
West Virginia Paving Inc. | 52,103.60 | |||
031 | S320-7-0.00 | KANAWHA | ||
West Virginia Paving Inc. | 60.312.50 | |||
Orders & Haynes Paving Co., Inc. | 61,726.70 | |||
032 | S323-2-1.52 | LOGAN | ||
Orders & Haynes Paving Co., Inc. | 16,678.30 | |||
West Virginia Paving Inc. | 16,927.90 | |||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 18,286.40 | |||
033 | S323-3/7-0.75 | LOGAN | ||
Mountain Enterprise Inc. dba Lenore Asphalt Inc. | 20,559.40 | |||
Orders & Haynes Paving Co., Inc. | 21,678.65 | |||
034 | S323-3.19-0.00 | LOGAN | ||
West Virginia Paving Inc. | 179,077.25 | |||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 198,763.00 | |||
035 | S323-3/35-0.00 | LOGAN | ||
Orders & Haynes Paving Co., Inc. | 27,354.90 | |||
West Virginia Paving Inc. | 28,727.00 | |||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 30,176.10 | |||
036 | S323-5/3-4.55 | LOGAN | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 46,680.40 | |||
037 | S323-5/7-0.00 | LOGAN | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 22,385.70 | |||
038 | S323-12-3.20 | LOGAN | ||
West Virginia Paving Inc. | 13,293.90 | |||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 13,899.40 | |||
039 | S327-25-6.57 | MASON | ||
West Virginia Paving Inc. | 106,857.80 | |||
Carl Kelly Paving Inc. | 115,500.00 | |||
040 | S328-9-7.48 | MERCER | ||
West Virginia Paving Inc. | 61,277.50 | |||
Bluestone Paving Inc. | 63,774.75 | |||
041 | S328-19-6.01 | MERCER | ||
Bluestone Paving Inc. | 221,069.55 | |||
West Virginia Paving Inc. | 224,454.07 | |||
042 | S328-38/4-0.00 | MERCER | ||
West Virginia Paving Inc. | 43,960.52 | |||
Bluestone Paving Inc. | 49,979.50 | |||
043 | S328-71/14-0.00 | MERCER | ||
West Virginia Paving Inc. | 21,332.48 | |||
Bluestone Paving Inc. | 27,481.50 | |||
044 | S330-10-4.64 | MINGO | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 66,005.00 | |||
045 | S330-13-6.84 | MINGO | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 61,718.50 | |||
046 | S332-24-0.96 | MONROE | ||
West Virginia Paving Inc. | 34,091.43 | |||
Bluestone Paving Inc. | 35,063.93 | |||
047 | S334-7/4-0.00 | NICHOLAS | ||
Waco Oil & Gas Co., Inc. | 47,913,75 | |||
West Virginia Paving Inc. | 54,223.60 | |||
048 | S334-18-0.00 | NICHOLAS | ||
Waco Oil & Gas Co., Inc. | 64,601.25 | |||
West Virginia Paving Inc. | 71,539.20 | |||
049 | S334-19/31-0.00 | NICHOLAS | ||
West Virginia Paving Inc. | 21,501.95 | |||
Meadows Stone & Paving | 42,797.50 | |||
050 | S334-20-18.14 | NICHOLAS | ||
West Virginia Paving Inc. | 152,826.23 | |||
051 | S334-39/18-0.60 | NICHOLAS | ||
Waco Oil & Gas Co., Inc. | 27,385.50 | |||
West Virginia Paving Inc. | 32,123.30 | |||
052 | S339-19-0.00 | PRESTON | ||
Mountaineer Contractors Inc. | 115,407.87 | |||
Dodd General Contractors | 119,985.09 | |||
Ohio Valley Paving Corp. | 124,089.82 | |||
Harman Construction | 154,482.65 | |||
053 | S339-33/12-0.00 | PRESTON | ||
Ohio Valley Paving Corp. | 45,648.60 | |||
Dodd General Contractors | 46,193.49 | |||
Harman Construction | 49,010.85 | |||
J.F. Allen Company | 49,620.40 | |||
Mountaineer Contractors Inc. | 49,677.24 | |||
054 | S340-33-0.00 | PUTNAM | ||
West Virginia Paving Inc. | 149,418.84 | |||
Orders & Haynes Paving Co., Inc. | 878,522.49 | |||
055 | S340-50-7.44 | PUTNAM | ||
Orders & Haynes Paving Co., Inc. | 73,798.07 | |||
West Virginia Paving Inc. | 74,583.73 | |||
056 | S341-27/14-0.00 | RALEIGH | ||
West Virginia Paving Inc. | 23,720.03 | |||
Bluestone Paving Inc. | 40,144.50 | |||
057 | S344-19-2.55 & S344-38/6-0.00 | ROANE | ||
Orders & Haynes Paving Co., Inc. | 259,027.13 | |||
West Virginia Paving Inc. | 295,169.31 | |||
Carl Kelly Paving Inc. | 362,532.45 | |||
058 | S345-11-3.46 | SUMMERS | ||
West Virginia Paving Inc. | 73,272.70 | |||
059 | S350-22-2.20 | WAYNE | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 39,566.33 | |||
Blacktop Industries Inc. | 42,342.30 | |||
060 | S350-24/2-0.00 | WAYNE | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 14,648.49 | |||
Blacktop Industries Inc. | 21,603.90 | |||
061 | S350-36-2.11 | WAYNE | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 27,369.10 | |||
Blacktop Industries Inc. | 30,650.90 | |||
062 | S350-52-37.50 | WAYNE | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 119,292.54 | |||
063 | S350-152-38.50 | WAYNE | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 37,656.75 | |||
064 | S354-1-1.68 | WOOD | ||
Carl Kelly Paving Inc. | 132,689.25 | |||
West Virginia Paving Inc. | 144,652.00 | |||
065 | S354-16-4.77 & S354-31-3.49 | WOOD | ||
Carl Kelly Paving Inc. | 234,135.58 | |||
West Virginia Paving Inc. | 274,202.46 | |||
066 | S354-25-6.78 | WOOD | ||
Carl Kelly Paving Inc. | 102,842.94 | |||
West Virginia Paving Inc. | 125,157.25 | |||
067 | S323-119/23-0.01 | LOGAN | ||
McCoy Construction | 424,350.00 | |||
Bilco Construction Company | 448,081.00 | |||
Orders Construction Co. | 541,662.50 | |||
Teays River Construction Co. | 549,510.00 | |||
068 | S348-66-0.01 | TYLER | ||
Upon This Rock Construction | 587,000.00 | |||
Turman Construction Co. | 651,297.75 | |||
Bilco Construction Company | 672,130.00 | |||
Teays River Construction | 678,671.00 | |||
Orders Construction Co. | 729,208.12 | |||
Alan Stone Co. | 776,378.77 | |||
069 | STP-0003(076)EQ S322-3-10.36 | LINCOLN | ||
Mountain Enterprises Inc. dba Lenore Asphalt Inc. | 1,224,029.87 | |||
West Virginia Paving Inc. | 1,287,268.83 | |||
Orders & Haynes Paving Co., Inc. | 1,351,570.34 | |||