1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -1 VENDOR RANKING CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 CONTRACT DESCRIPTION : JEFFERSON STREET BRIDGE #1567.2 REPAIR PROJECT(S) : S325-0019/73-000.09 00 ACDP 0077 085 E LOCATION: 0.09 MILES EAST OF US 19 0 -------------------------------------------------------------------------------------------------------------------------- TOTAL % OVER RANK VENDOR NO./NAME BID LOW BID -------------------------------------------------------------------------------------------------------------------------- 1 25-1100215 MOSITES CONSTRUCTION COMPANY $ 20,643,266.00 100.0000% 2 34-0420560 NATIONAL ENGINEERING & CONTRACTING COMPANY $ 22,160,982.10 107.3521% 3 25-1021993 TRUMBULL CORPORATION $ 22,917,963.85 111.0190% 4 47-0640263 KIEWIT CONSTRUCTION COMPANY $ 23,023,913.00 111.5323% 5 62-1345425 BILCO CONSTRUCTION COMPANY, INC. $ 24,344,590.00 117.9299% 25-1355037 DICK CORPORATION IRREGULAR 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -2 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(1) 25-1100215 |(2) 34-0420560 |(3) 25-1021993 |MOSITES CONSTRUCTION COMPANY|NATIONAL ENGINEERING & CONTR|TRUMBULL CORPORATION LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 1.000 LS | 50000.00000 50000.00| 70000.00000 70000.00| 50000.00000 50000.00 CLEARING AND GRUBBING | | | 0010 202-01 1.000 LS | 25000.00000 25000.00| 10000.00000 10000.00| 40000.00000 40000.00 BUILDING DEMOLITION | | | 0015 204-01 LUMP| 25000.00000 25000.00| 660000.00000 660000.00| 650000.00000 650000.00 MOBILIZATION | | | 0020 207-02 30.000 M3 | 40.00000 1200.00| 90.00000 2700.00| 140.00000 4200.00 SUBGRADE | | | 0025 218-07 140.000 M2 | 4.00000 560.00| 7.00000 980.00| 3.80000 532.00 FABRIC FOR EROSION CONTROL | | | 0030 307-01 50.000 M3 | 76.00000 3800.00| 85.00000 4250.00| 150.00000 7500.00 CLASS I AGGREGATE BASE COURSE | | | 0035 408-02 220.000 L | 0.50000 110.00| 1.00000 220.00| 1.50000 330.00 BITUMINOUS MATERIAL | | | 0040 501-01250 40.000 M2 | 70.00000 2800.00| 140.00000 5600.00| 130.00000 5200.00 REIN PORTLAND CEMENT CONCRETE PAVEMENT | | | 250MM | | | 0045 502-01300 162.000 M2 | 150.00000 24300.00| 150.00000 24300.00| 200.00000 32400.00 PORTLAND CEMENT CONCRETE APPRACH SLAB | | | 300MM | | | 0050 601-02 1.000 M3 | 500.00000 500.00| 2000.00000 2000.00| 1100.00000 1100.00 CLASS B CONCRETE | | | 0055 604-3704503 93.000 M | 200.00000 18600.00| 300.00000 27900.00| 360.00000 33480.00 REINFORCED CONCRETE PIPE, 450MM, CLIII | | | 0060 604-3706003 52.000 M | 280.00000 14560.00| 450.00000 23400.00| 380.00000 19760.00 REINFORCED CONCRETE PIPE, 600MM, CLASS | | | III | | | 0065 604-540600V 30.000 M | 2000.00000 60000.00| 1700.00000 51000.00| 1250.00000 37500.00 JACKED CONDUIT, REINFORCED CONCRETE | | | PIPE 600MM, CLASS V | | | 0070 604-760450A2 11.000 M | 170.00000 1870.00| 360.00000 3960.00| 220.00000 2420.00 ALUMINUM COATED CORRUGATED STEEL PIPE, | | | 450MM, A2 | | | 0075 604-760600A2 25.000 M | 190.00000 4750.00| 400.00000 10000.00| 170.00000 4250.00 ALUMINUM COATED CORRUGATED STEEL PIPE, | | | 600MM, A2 | | | 0080 605-01 4.000 EA | 3100.00000 12400.00| 3250.00000 13000.00| 2100.00000 8400.00 TYPE A MANHOLE | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -3 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(1) 25-1100215 |(2) 34-0420560 |(3) 25-1021993 |MOSITES CONSTRUCTION COMPANY|NATIONAL ENGINEERING & CONTR|TRUMBULL CORPORATION LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0085 605-011 2.000 EA | 4100.00000 8200.00| 3250.00000 6500.00| 2500.00000 5000.00 TYPE A MANHOLE, MODIFIED | | | 0090 605-03 3.000 EA | 2700.00000 8100.00| 2500.00000 7500.00| 2600.00000 7800.00 TYPE A INLET | | | 0095 605-04 3.000 EA | 2100.00000 6300.00| 2500.00000 7500.00| 2150.00000 6450.00 TYPE B INLET | | | 0100 605-05 1.000 EA | 2700.00000 2700.00| 2500.00000 2500.00| 2800.00000 2800.00 TYPE C INLET | | | 0105 605-08 1.000 EA | 3100.00000 3100.00| 2500.00000 2500.00| 2900.00000 2900.00 TYPE F INLET | | | 0110 605-15 2.000 EA | 1000.00000 2000.00| 1000.00000 2000.00| 300.00000 600.00 ADJUST EXISTING MANHOLE | | | 0115 606-200300 109.000 M | 30.00000 3270.00| 50.00000 5450.00| 19.00000 2071.00 AGGREGATE FILL FABRIC UNDERDRAIN 300MM | | | 0120 606-250100 109.000 M | 4.00000 436.00| 30.00000 3270.00| 5.50000 599.50 UNDERDRAIN PIPE 100MM | | | 0125 608-0118 237.000 M | 63.00000 14931.00| 70.00000 16590.00| 70.00000 16590.00 RIGHT OF WAY FENCE CHAIN LINK 1.8M | | | 0130 608-053 1.000 EA | 700.00000 700.00| 800.00000 800.00| 850.00000 850.00 VEHICULAR GATE CHAIN LINK 3M | | | 0135 609-01 433.000 M2 | 60.00000 25980.00| 42.00000 18186.00| 45.00000 19485.00 CONCRETE SIDEWALK | | | 0140 609-02 63.000 M3 | 50.00000 3150.00| 85.00000 5355.00| 85.00000 5355.00 BED COURSE MATERIAL | | | 0145 610-011 46.000 M | 100.00000 4600.00| 100.00000 4600.00| 100.00000 4600.00 PLAIN CONCRETE CURBING, TYPE I | | | 0150 610-021 37.000 M | 120.00000 4440.00| 85.00000 3145.00| 85.00000 3145.00 INTEGRAL CONCRETE CURBING TYPE I | | | 0155 610-021 30.000 M | 80.00000 2400.00| 85.00000 2550.00| 85.00000 2550.00 INTEGRAL CONCRETE CURBING TYPE I | | | MODIFIED 610-021-1 | | | 0160 633-03 90.000 M3 | 110.00000 9900.00| 75.00000 6750.00| 60.00000 5400.00 DUMPED ROCK GUTTER | | | 0165 636-11 10855.000 UN | 3.00000 32565.00| 1.30000 14111.50| 3.50000 37992.50 TRAFFIC CONTROL DEVICE | | | 0170 636-12 5.000 EA | 200.00000 1000.00| 200.00000 1000.00| 220.00000 1100.00 CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0175 636-13 200.000 EA | 3.00000 600.00| 3.00000 600.00| 3.25000 650.00 CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -4 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(1) 25-1100215 |(2) 34-0420560 |(3) 25-1021993 |MOSITES CONSTRUCTION COMPANY|NATIONAL ENGINEERING & CONTR|TRUMBULL CORPORATION LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0180 636-14 1000.000 HR | 32.00000 32000.00| 35.00000 35000.00| 35.00000 35000.00 FLAGGER | | | 0185 636-17 55.000 M | 60.00000 3300.00| 90.00000 4950.00| 100.00000 5500.00 TEMPORARY CONCRETE BARRIERS | | | 0190 636-21 20.000 DA | 20.00000 400.00| 21.00000 420.00| 150.00000 3000.00 ELECTRIC ARROW | | | 0195 636-23 LUMP| 20000.00000 20000.00| 21000.00000 21000.00| 25000.00000 25000.00 TEMPORARY TRAFFIC SIGNAL 636-2302 | | | 0200 636-25A 5700.000 DA | 1.00000 5700.00| 0.55000 3135.00| 0.70000 3990.00 WARNING LIGHTS TYPE A | | | 0205 636-25B 2200.000 DA | 2.00000 4400.00| 1.80000 3960.00| 1.90000 4180.00 WARNING LIGHTS TYPE B | | | 0210 638-02 17.000 EA | 30.00000 510.00| 130.00000 2210.00| 45.00000 765.00 RIGHT OF WAY MARKERS | | | 0215 639-01 LUMP| 5000.00000 5000.00| 450000.00000 450000.00| 120000.00000 120000.00 CONSTRUCTION LAYOUT STAKES | | | 0220 640-01 LUMP| 30000.00000 30000.00| 80000.00000 80000.00| 80000.00000 80000.00 STANDARD FIELD OFFICE AND STORAGE | | | BUILDING | | | 0225 640-03 LUMP| 1000.00000 1000.00| 25000.00000 25000.00| 10000.00000 10000.00 BUILDING EQUIPMENT | | | 0235 642-14 LUMP| 500.00000 500.00| 10000.00000 10000.00| 15000.00000 15000.00 TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 0240 670-16 1.000 EA | 1000.00000 1000.00| 900.00000 900.00| 1500.00000 1500.00 RELOCATE METER | | | 0245 670-2125 64.000 M | 100.00000 6400.00| 125.00000 8000.00| 120.00000 7680.00 HOUSE CONNECTION 25MM | | | 0250 675-07300 6.000 M | 200.00000 1200.00| 250.00000 1500.00| 680.00000 4080.00 PLASTIC SEWER PIPE 300MM | | | 0255 675-08600152 6.000 M | 400.00000 2400.00| 550.00000 3300.00| 700.00000 4200.00 DUCTILE IRON SEWER PIPE TYPE 1, CLASS | | | 52, 600MM | | | 0260 681-01 LUMP| 5000.00000 5000.00| 8000.00000 8000.00| 8000.00000 8000.00 ASBESTOS ABATEMENT 681-01(01) | | | 0265 402-01SG AA1 40.000 MGR | 200.00000 8000.00| 200.00000 8000.00| 150.00000 6000.00 HMA SKID PAVEMENT, STONE/GRAVEL | | | 0270 402-01S AA2 40.000 MGR | | | HMA SKID PAVEMENT, SLAG | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -5 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(1) 25-1100215 |(2) 34-0420560 |(3) 25-1021993 |MOSITES CONSTRUCTION COMPANY|NATIONAL ENGINEERING & CONTR|TRUMBULL CORPORATION LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION TOTALS | $ 506,632.00| $ 1,685,592.50| $ 1,356,905.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 TRAFFIC SIGNALS | | | 0275 660-01 LUMP| 14000.00000 14000.00| 13500.00000 13500.00| 13500.00000 13500.00 SIGNAL CONTROLLERS 660-01(01) | | | 0280 660-01 LUMP| 14000.00000 14000.00| 13500.00000 13500.00| 13500.00000 13500.00 SIGNAL CONTROLLERS 660-01(02) | | | 0285 660-02LPSC 5.000 EA | 200.00000 1000.00| 200.00000 1000.00| 165.00000 825.00 TRAFFIC DETECTORS | | | 0290 660-03G407 14.000 EA | 1000.00000 14000.00| 950.00000 13300.00| 1000.00000 14000.00 SIGNAL SECTIONS | | | 0295 660-03V305 52.000 EA | 200.00000 10400.00| 200.00000 10400.00| 200.00000 10400.00 SIGNAL SECTIONS | | | 0300 660-04A1 6.000 EA | 11000.00000 66000.00| 10500.00000 63000.00| 11000.00000 66000.00 SIGNAL SUPPORTS | | | 0305 660-04E1 3.000 EA | 4000.00000 12000.00| 4000.00000 12000.00| 4173.75000 12521.25 SIGNAL SUPPORTS | | | 0310 660-05H 12.000 EA | 900.00000 10800.00| 900.00000 10800.00| 1200.00000 14400.00 JUNCTION BOXES TYPE H | | | 0315 660-06 LUMP| 18000.00000 18000.00| 17500.00000 17500.00| 23000.00000 23000.00 SIGNAL INTERCONNECT 660-061 | | | 0320 660-07 LUMP| 22000.00000 22000.00| 22000.00000 22000.00| 25000.00000 25000.00 MISCELLANEOUS SIGNAL 660-07(01) | | | 0325 660-07 LUMP| 65000.00000 65000.00| 63000.00000 63000.00| 65000.00000 65000.00 MISCELLANEOUS SIGNAL 660-07(02) | | | SECTION TOTALS | $ 247,200.00| $ 240,000.00| $ 258,146.25 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0003 PAVEMENT MARKINGS | | | 0330 663-0112W 850.000 M | 1.00000 850.00| 1.20000 1020.00| 1.20000 1020.00 EDGE LINE WHITE TYPE II | | | 0335 663-0212W 210.000 M | 1.00000 210.00| 1.50000 315.00| 1.30000 273.00 LANE LINE OR CENTER LINE WHITE TYPE II | | | 0340 663-0312 810.000 M | 1.00000 810.00| 1.20000 972.00| 1.20000 972.00 BARRIER LINES TYPE II | | | 0345 663-055 50.000 M | 50.00000 2500.00| 45.00000 2250.00| 45.00000 2250.00 TYPE V STOP LINES | | | 0350 663-065 200.000 M | 12.00000 2400.00| 18.00000 3600.00| 12.50000 2500.00 TYPE V CROSSWALK LINES | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -6 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(1) 25-1100215 |(2) 34-0420560 |(3) 25-1021993 |MOSITES CONSTRUCTION COMPANY|NATIONAL ENGINEERING & CONTR|TRUMBULL CORPORATION LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0355 663-105 6.000 EA | 230.00000 1380.00| 300.00000 1800.00| 220.00000 1320.00 TYPE V LANE ARROWS | | | 0360 663-115 8.000 EA | 80.00000 640.00| 90.00000 720.00| 80.00000 640.00 TYPE V LANE LETTERS | | | SECTION TOTALS | $ 8,790.00| $ 10,677.00| $ 8,975.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0004 BRIDGE # 1567.2 | | | 0365 203-01 LUMP| 25000.00000 25000.00| 100000.00000 100000.00| 50000.00000 50000.00 DISMANTLING STRUCTURES 203-01(1) | | | ABANDONED RAILROAD BRIDGE | | | 0370 203-01 LUMP| 4000000.00000 4000000.00| 3360000.00000 3360000.00| 2000000.00000 2000000.00 DISMANTLING STRUCTURES 203-01(2) | | | JEFFERSON STREET BRIDGE | | | 0375 212-01 354.000 M3 | 30.00000 10620.00| 40.00000 14160.00| 50.00000 17700.00 STRUCTURE EXCAVATION | | | 0380 212-05 400.000 M3 | 50.00000 20000.00| 80.00000 32000.00| 50.00000 20000.00 SELECT MATERIAL FOR BACKFILLING | | | 0385 218-04200 2630.000 M2 | 25.00000 65750.00| 25.00000 65750.00| 19.00000 49970.00 CRUSHED ROCK SLOPE PROTECTION 200MM | | | 0390 601-02 1127.000 M3 | 2000.00000 2254000.00| 880.00000 991760.00| 1400.00000 1577800.00 CLASS B CONCRETE | | | 0395 601-02-1 1.000 M3 | 20000.00000 20000.00| 45000.00000 45000.00| 25000.00000 25000.00 CLASS B CONCRETE, MODIFIED | | | 0400 601-03 1698.000 M3 | 600.00000 1018800.00| 630.00000 1069740.00| 670.00000 1137660.00 CLASS K CONCRETE | | | 0405 601-03(05) 260.000 M3 | 2000.00000 520000.00| 1700.00000 442000.00| 3550.00000 923000.00 CLASS K CONCRETE BRIDGE RAILING | | | 0410 602-01 67596.000 KG | 2.00000 135192.00| 2.00000 135192.00| 2.20000 148711.20 REIN STEEL BARS | | | 0415 602-02 273386.000 KG | 2.00000 546772.00| 1.60000 437417.60| 1.40000 382740.40 EPOXY COATED REINFORCING BARS | | | 0420 615-03 1.000 LS | 450000.00000 450000.00| 400000.00000 400000.00| 600000.00000 600000.00 FABRICATED STRUCTURAL STEEL | | | 0425 625-19 34.000 M | 600.00000 20400.00| 700.00000 23800.00| 1400.00000 47600.00 ELASTOMERIC CONCRETE STRIP SEAL | | | EXPANSION DAM | | | 0430 643-01 100.000 WK | 100.00000 10000.00| 325.00000 32500.00| 320.00000 32000.00 PROGRESS PHOTOGRAPHS | | | 0435 643-02 12.000 EA | 10.00000 120.00| 250.00000 3000.00| 40.00000 480.00 ADDITIONAL PHOTOGRAPHS, PER PHOTO FILED | | | TRIP | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -7 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(1) 25-1100215 |(2) 34-0420560 |(3) 25-1021993 |MOSITES CONSTRUCTION COMPANY|NATIONAL ENGINEERING & CONTR|TRUMBULL CORPORATION LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0440 679-06 LUMP| 2500.00000 2500.00| 2500.00000 2500.00| 3000.00000 3000.00 TEST SLAB | | | 0445 JB-1 4.000 EA | 20000.00000 80000.00| 20000.00000 80000.00| 20000.00000 80000.00 EAGLE FINIALS, FLAGPOLES AND FLAGPOLE | | | BASE LIGHTING | | | 0450 JB-2 LUMP| 20000.00000 20000.00| 50000.00000 50000.00| 95000.00000 95000.00 STANDARD STEEL DOORS, ALUMINUM WINDOWS | | | AND GLASS BLOCK | | | 0455 JB-5 100.000 M2 | 300.00000 30000.00| 1250.00000 125000.00| 1350.00000 135000.00 CLASS 1 CONCRETE REPAIRS | | | 0460 JB-6 30.000 M3 | 8000.00000 240000.00| 13500.00000 405000.00| 14100.00000 423000.00 CLASS 2 CONCRETE REPAIRS | | | 0465 JB-7 4000.000 M | 90.00000 360000.00| 21.00000 84000.00| 22.00000 88000.00 CRACK REPAIRS | | | 0470 JB-9 LUMP| 500000.00000 500000.00| 600000.00000 600000.00| 1600000.00000 1600000.00 SUPPORT OF BELL ATLANTIC CABLES | | | 0475 679-02 BB1 163.000 M3 | | | LATEX MODIFIED PORTLAND CEMENT MORTAR | | | OR CONCRETE OVERLAYMENT OF BRIDGE DECK | | | 0480 679-04 BB2 163.000 M3 | 800.00000 130400.00| 740.00000 120620.00| 1040.00000 169520.00 MICROSILICA CONCRETE OVERLAY | | | SECTION TOTALS | $ 10,459,554.00| $ 8,619,439.60| $ 9,606,181.60 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0005 BRIDGE AND NAVIGATION LIGHTING | | | 0485 662-02 LUMP| 23000.00000 23000.00| 22000.00000 22000.00| 24000.00000 24000.00 GALVANIZED STEEL CONDUIT 662-021 | | | 0490 662-02 LUMP| 5500.00000 5500.00| 5000.00000 5000.00| 5500.00000 5500.00 GALVANIZED STEEL CONDUIT 662-022 | | | 0495 662-06L 56.000 EA | 500.00000 28000.00| 500.00000 28000.00| 470.00000 26320.00 JUNCTION BOX | | | 0500 662-0750 104.000 EA | 2400.00000 249600.00| 2400.00000 249600.00| 2500.00000 260000.00 LUMINAIRES 50W HPS | | | 0505 662-10 40.000 EA | 16000.00000 640000.00| 17000.00000 680000.00| 17700.00000 708000.00 LIGHTING SUPPORT TYPE 6 | | | 0510 662-081 LUMP| 65000.00000 65000.00| 64000.00000 64000.00| 65000.00000 65000.00 CABLE | | | 0515 662-082 LUMP| 20000.00000 20000.00| 19000.00000 19000.00| 19000.00000 19000.00 CABLE | | | 0520 662-13 LUMP| 23000.00000 23000.00| 23000.00000 23000.00| 23000.00000 23000.00 SERVICE AND CONTROL STATION 662-131 | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -8 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(1) 25-1100215 |(2) 34-0420560 |(3) 25-1021993 |MOSITES CONSTRUCTION COMPANY|NATIONAL ENGINEERING & CONTR|TRUMBULL CORPORATION LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0525 662-13 LUMP| 20000.00000 20000.00| 20000.00000 20000.00| 20000.00000 20000.00 SERVICE AND CONTROL STATION 662-132 | | | 0530 662-14 LUMP| 15000.00000 15000.00| 14000.00000 14000.00| 14000.00000 14000.00 INCIDENTAL ELECTRICAL WORK | | | 0535 662-15 LUMP| 110.00000 110.00| 100.00000 100.00| 100.00000 100.00 ELECTRICAL TESTS 662-151 | | | 0540 662-15 LUMP| 110.00000 110.00| 100.00000 100.00| 100.00000 100.00 ELECTRICAL TESTS 662-152 | | | 0545 662-20 LUMP| 60000.00000 60000.00| 60000.00000 60000.00| 60000.00000 60000.00 NAVIGATION LIGHTING SYSTEM | | | SECTION TOTALS | $ 1,149,320.00| $ 1,184,800.00| $ 1,225,020.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0006 SPECIALITY ITEMS | | | 0550 603-18(710) 351.000 M | 300.00000 105300.00| 320.00000 112320.00| 428.00000 150228.00 PRESTRESSED CONCRETE I BEAMS 710MM | | | 0555 603-18(915) 235.000 M | 400.00000 94000.00| 380.00000 89300.00| 460.00000 108100.00 PRESTRESSED CONCRETE I BEAMS 915MM | | | 0560 603-20(150) 2848.000 M2 | 200.00000 569600.00| 175.00000 498400.00| 275.00000 783200.00 PRESTRESSED CONCRETE DECK PANELS 150MM | | | 0565 603-20(250) 1163.000 M2 | 400.00000 465200.00| 320.00000 372160.00| 330.00000 383790.00 PRESTRESSED CONCRETE DECK PANELS 250MM | | | 0570 603-21(250) 546.000 M2 | 400.00000 218400.00| 440.00000 240240.00| 365.00000 199290.00 PRECAST CONCRETE DECK PANELS 250MM | | | 0575 603-22 433.000 M | 500.00000 216500.00| 725.00000 313925.00| 480.00000 207840.00 PRECAST CONCRETE SPANDREL BEAMS | | | 0580 603-23 1825.000 M2 | 1170.00000 2135250.00| 1650.00000 3011250.00| 1680.00000 3066000.00 PRECAST CONCRETE RIB WALLS | | | 0585 603-24 894.000 M | 1010.00000 902940.00| 1000.00000 894000.00| 1050.00000 938700.00 PRECAST CONCRETE CAP BEAMS | | | 0590 603-25 273.000 M2 | 1400.00000 382200.00| 2700.00000 737100.00| 2350.00000 641550.00 PRECAST ARCHITECTURAL CONCRETE | | | 0595 603-26 469.000 M | 500.00000 234500.00| 560.00000 262640.00| 500.00000 234500.00 PRECAST CONCRETE - JB BEAMS | | | 0600 JB-3 370.000 M3 | 4000.00000 1480000.00| 5100.00000 1887000.00| 5250.00000 1942500.00 SHOTCRETE REPAIRS | | | 0605 JB-4 LUMP| 15000.00000 15000.00| 5000.00000 5000.00| 2500.00000 2500.00 SHOTCRETE TEST PANELS | | | 0610 JB-8 6400.000 M2 | 150.00000 960000.00| 230.00000 1472000.00| 200.00000 1280000.00 SHOTCRETE OVERLAY | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -9 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(1) 25-1100215 |(2) 34-0420560 |(3) 25-1021993 |MOSITES CONSTRUCTION COMPANY|NATIONAL ENGINEERING & CONTR|TRUMBULL CORPORATION LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0615 631-06(01) LUMP| 100000.00000 100000.00| 115000.00000 115000.00| 115000.00000 115000.00 RECTIFIER SYSTEM | | | 0620 631-06(02) 36.000 EA | 200.00000 7200.00| 200.00000 7200.00| 210.00000 7560.00 REFERENCE CELL | | | 0625 631-06(03) 4734.000 M2 | 70.00000 331380.00| 67.00000 317178.00| 67.00000 317178.00 ANODE SYSTEM | | | 0630 631-11 20.000 EA | 70.00000 1400.00| 68.00000 1360.00| 70.00000 1400.00 CONTINUITY BONDS | | | 0635 631-12 LUMP| 50000.00000 50000.00| 70000.00000 70000.00| 75000.00000 75000.00 CORRISION ENGINEERING SERVICES | | | SECTION TOTALS | $ 8,268,870.00| $ 10,406,073.00| $ 10,454,336.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0007 COMPUTER SYSTEM | | | 0645 640-04 LUMP| 500.00000 500.00| 12000.00000 12000.00| 6000.00000 6000.00 COMPUTER SYSTEM FOR FIELD OFFICE | | | SECTION TOTALS | $ 500.00| $ 12,000.00| $ 6,000.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0008 TRAINING | | | 0650 699 3000.000 HR | 0.80000 2400.00| 0.80000 2400.00| 0.80000 2400.00 ON JOB TRAINING | | | SECTION TOTALS | $ 2,400.00| $ 2,400.00| $ 2,400.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 20,643,266.00| $ 22,160,982.10| $ 22,917,963.85 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -10 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(4) 47-0640263 |(5) 62-1345425 | |KIEWIT CONSTRUCTION COMPANY |BILCO CONSTRUCTION COMPANY, | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 1.000 LS | 100000.00000 100000.00| 75000.00000 75000.00| CLEARING AND GRUBBING | | | 0010 202-01 1.000 LS | 25000.00000 25000.00| 15000.00000 15000.00| BUILDING DEMOLITION | | | 0015 204-01 LUMP| 450000.00000 450000.00| 275000.00000 275000.00| MOBILIZATION | | | 0020 207-02 30.000 M3 | 140.00000 4200.00| 60.00000 1800.00| SUBGRADE | | | 0025 218-07 140.000 M2 | 20.00000 2800.00| 3.00000 420.00| FABRIC FOR EROSION CONTROL | | | 0030 307-01 50.000 M3 | 100.00000 5000.00| 60.00000 3000.00| CLASS I AGGREGATE BASE COURSE | | | 0035 408-02 220.000 L | 4.00000 880.00| 0.50000 110.00| BITUMINOUS MATERIAL | | | 0040 501-01250 40.000 M2 | 120.00000 4800.00| 100.00000 4000.00| REIN PORTLAND CEMENT CONCRETE PAVEMENT | | | 250MM | | | 0045 502-01300 162.000 M2 | 170.00000 27540.00| 160.00000 25920.00| PORTLAND CEMENT CONCRETE APPRACH SLAB | | | 300MM | | | 0050 601-02 1.000 M3 | 3500.00000 3500.00| 2000.00000 2000.00| CLASS B CONCRETE | | | 0055 604-3704503 93.000 M | 350.00000 32550.00| 275.00000 25575.00| REINFORCED CONCRETE PIPE, 450MM, CLIII | | | 0060 604-3706003 52.000 M | 300.00000 15600.00| 330.00000 17160.00| REINFORCED CONCRETE PIPE, 600MM, CLASS | | | III | | | 0065 604-540600V 30.000 M | 1500.00000 45000.00| 440.00000 13200.00| JACKED CONDUIT, REINFORCED CONCRETE | | | PIPE 600MM, CLASS V | | | 0070 604-760450A2 11.000 M | 170.00000 1870.00| 275.00000 3025.00| ALUMINUM COATED CORRUGATED STEEL PIPE, | | | 450MM, A2 | | | 0075 604-760600A2 25.000 M | 300.00000 7500.00| 330.00000 8250.00| ALUMINUM COATED CORRUGATED STEEL PIPE, | | | 600MM, A2 | | | 0080 605-01 4.000 EA | 3600.00000 14400.00| 3850.00000 15400.00| TYPE A MANHOLE | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -11 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(4) 47-0640263 |(5) 62-1345425 | |KIEWIT CONSTRUCTION COMPANY |BILCO CONSTRUCTION COMPANY, | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0085 605-011 2.000 EA | 3800.00000 7600.00| 4950.00000 9900.00| TYPE A MANHOLE, MODIFIED | | | 0090 605-03 3.000 EA | 2500.00000 7500.00| 2750.00000 8250.00| TYPE A INLET | | | 0095 605-04 3.000 EA | 2400.00000 7200.00| 2530.00000 7590.00| TYPE B INLET | | | 0100 605-05 1.000 EA | 2600.00000 2600.00| 3850.00000 3850.00| TYPE C INLET | | | 0105 605-08 1.000 EA | 2600.00000 2600.00| 3850.00000 3850.00| TYPE F INLET | | | 0110 605-15 2.000 EA | 260.00000 520.00| 2420.00000 4840.00| ADJUST EXISTING MANHOLE | | | 0115 606-200300 109.000 M | 80.00000 8720.00| 32.00000 3488.00| AGGREGATE FILL FABRIC UNDERDRAIN 300MM | | | 0120 606-250100 109.000 M | 30.00000 3270.00| 40.00000 4360.00| UNDERDRAIN PIPE 100MM | | | 0125 608-0118 237.000 M | 40.00000 9480.00| 60.00000 14220.00| RIGHT OF WAY FENCE CHAIN LINK 1.8M | | | 0130 608-053 1.000 EA | 1000.00000 1000.00| 715.00000 715.00| VEHICULAR GATE CHAIN LINK 3M | | | 0135 609-01 433.000 M2 | 120.00000 51960.00| 90.00000 38970.00| CONCRETE SIDEWALK | | | 0140 609-02 63.000 M3 | 160.00000 10080.00| 50.00000 3150.00| BED COURSE MATERIAL | | | 0145 610-011 46.000 M | 180.00000 8280.00| 200.00000 9200.00| PLAIN CONCRETE CURBING, TYPE I | | | 0150 610-021 37.000 M | 130.00000 4810.00| 250.00000 9250.00| INTEGRAL CONCRETE CURBING TYPE I | | | 0155 610-021 30.000 M | 150.00000 4500.00| 250.00000 7500.00| INTEGRAL CONCRETE CURBING TYPE I | | | MODIFIED 610-021-1 | | | 0160 633-03 90.000 M3 | 70.00000 6300.00| 65.00000 5850.00| DUMPED ROCK GUTTER | | | 0165 636-11 10855.000 UN | 5.00000 54275.00| 1.40000 15197.00| TRAFFIC CONTROL DEVICE | | | 0170 636-12 5.000 EA | 1200.00000 6000.00| 0.20000 1.00| CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0175 636-13 200.000 EA | 70.00000 14000.00| 0.05000 10.00| CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -12 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(4) 47-0640263 |(5) 62-1345425 | |KIEWIT CONSTRUCTION COMPANY |BILCO CONSTRUCTION COMPANY, | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0180 636-14 1000.000 HR | 50.00000 50000.00| 60.00000 60000.00| FLAGGER | | | 0185 636-17 55.000 M | 200.00000 11000.00| 50.00000 2750.00| TEMPORARY CONCRETE BARRIERS | | | 0190 636-21 20.000 DA | 100.00000 2000.00| 35.00000 700.00| ELECTRIC ARROW | | | 0195 636-23 LUMP| 25000.00000 25000.00| 24000.00000 24000.00| TEMPORARY TRAFFIC SIGNAL 636-2302 | | | 0200 636-25A 5700.000 DA | 0.80000 4560.00| 0.75000 4275.00| WARNING LIGHTS TYPE A | | | 0205 636-25B 2200.000 DA | 1.75000 3850.00| 2.50000 5500.00| WARNING LIGHTS TYPE B | | | 0210 638-02 17.000 EA | 140.00000 2380.00| 100.00000 1700.00| RIGHT OF WAY MARKERS | | | 0215 639-01 LUMP| 400000.00000 400000.00| 50000.00000 50000.00| CONSTRUCTION LAYOUT STAKES | | | 0220 640-01 LUMP| 75000.00000 75000.00| 60000.00000 60000.00| STANDARD FIELD OFFICE AND STORAGE | | | BUILDING | | | 0225 640-03 LUMP| 30000.00000 30000.00| 10000.00000 10000.00| BUILDING EQUIPMENT | | | 0235 642-14 LUMP| 50000.00000 50000.00| 14000.00000 14000.00| TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 0240 670-16 1.000 EA | 750.00000 750.00| 2200.00000 2200.00| RELOCATE METER | | | 0245 670-2125 64.000 M | 45.00000 2880.00| 83.00000 5312.00| HOUSE CONNECTION 25MM | | | 0250 675-07300 6.000 M | 160.00000 960.00| 110.00000 660.00| PLASTIC SEWER PIPE 300MM | | | 0255 675-08600152 6.000 M | 350.00000 2100.00| 385.00000 2310.00| DUCTILE IRON SEWER PIPE TYPE 1, CLASS | | | 52, 600MM | | | 0260 681-01 LUMP| 5000.00000 5000.00| 7000.00000 7000.00| ASBESTOS ABATEMENT 681-01(01) | | | 0265 402-01SG AA1 40.000 MGR | 175.00000 7000.00| 190.00000 7600.00| HMA SKID PAVEMENT, STONE/GRAVEL | | | 0270 402-01S AA2 40.000 MGR | | | HMA SKID PAVEMENT, SLAG | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -13 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(4) 47-0640263 |(5) 62-1345425 | |KIEWIT CONSTRUCTION COMPANY |BILCO CONSTRUCTION COMPANY, | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION TOTALS | $ 1,623,815.00| $ 893,058.00| ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 TRAFFIC SIGNALS | | | 0275 660-01 LUMP| 8700.00000 8700.00| 14300.00000 14300.00| SIGNAL CONTROLLERS 660-01(01) | | | 0280 660-01 LUMP| 8900.00000 8900.00| 14300.00000 14300.00| SIGNAL CONTROLLERS 660-01(02) | | | 0285 660-02LPSC 5.000 EA | 140.00000 700.00| 200.00000 1000.00| TRAFFIC DETECTORS | | | 0290 660-03G407 14.000 EA | 440.00000 6160.00| 1000.00000 14000.00| SIGNAL SECTIONS | | | 0295 660-03V305 52.000 EA | 150.00000 7800.00| 210.00000 10920.00| SIGNAL SECTIONS | | | 0300 660-04A1 6.000 EA | 6000.00000 36000.00| 7000.00000 42000.00| SIGNAL SUPPORTS | | | 0305 660-04E1 3.000 EA | 1500.00000 4500.00| 1600.00000 4800.00| SIGNAL SUPPORTS | | | 0310 660-05H 12.000 EA | 1200.00000 14400.00| 1400.00000 16800.00| JUNCTION BOXES TYPE H | | | 0315 660-06 LUMP| 20000.00000 20000.00| 25000.00000 25000.00| SIGNAL INTERCONNECT 660-061 | | | 0320 660-07 LUMP| 25000.00000 25000.00| 27000.00000 27000.00| MISCELLANEOUS SIGNAL 660-07(01) | | | 0325 660-07 LUMP| 40000.00000 40000.00| 46000.00000 46000.00| MISCELLANEOUS SIGNAL 660-07(02) | | | SECTION TOTALS | $ 172,160.00| $ 216,120.00| ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0003 PAVEMENT MARKINGS | | | 0330 663-0112W 850.000 M | 0.70000 595.00| 1.00000 850.00| EDGE LINE WHITE TYPE II | | | 0335 663-0212W 210.000 M | 0.80000 168.00| 1.00000 210.00| LANE LINE OR CENTER LINE WHITE TYPE II | | | 0340 663-0312 810.000 M | 0.70000 567.00| 1.00000 810.00| BARRIER LINES TYPE II | | | 0345 663-055 50.000 M | 40.00000 2000.00| 50.00000 2500.00| TYPE V STOP LINES | | | 0350 663-065 200.000 M | 14.00000 2800.00| 13.00000 2600.00| TYPE V CROSSWALK LINES | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -14 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(4) 47-0640263 |(5) 62-1345425 | |KIEWIT CONSTRUCTION COMPANY |BILCO CONSTRUCTION COMPANY, | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0355 663-105 6.000 EA | 190.00000 1140.00| 225.00000 1350.00| TYPE V LANE ARROWS | | | 0360 663-115 8.000 EA | 65.00000 520.00| 100.00000 800.00| TYPE V LANE LETTERS | | | SECTION TOTALS | $ 7,790.00| $ 9,120.00| ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0004 BRIDGE # 1567.2 | | | 0365 203-01 LUMP| 150000.00000 150000.00| 250000.00000 250000.00| DISMANTLING STRUCTURES 203-01(1) | | | ABANDONED RAILROAD BRIDGE | | | 0370 203-01 LUMP| 6200000.00000 6200000.00| 4452000.00000 4452000.00| DISMANTLING STRUCTURES 203-01(2) | | | JEFFERSON STREET BRIDGE | | | 0375 212-01 354.000 M3 | 25.00000 8850.00| 45.00000 15930.00| STRUCTURE EXCAVATION | | | 0380 212-05 400.000 M3 | 70.00000 28000.00| 80.00000 32000.00| SELECT MATERIAL FOR BACKFILLING | | | 0385 218-04200 2630.000 M2 | 7.00000 18410.00| 38.00000 99940.00| CRUSHED ROCK SLOPE PROTECTION 200MM | | | 0390 601-02 1127.000 M3 | 2500.00000 2817500.00| 1000.00000 1127000.00| CLASS B CONCRETE | | | 0395 601-02-1 1.000 M3 | 10000.00000 10000.00| 10000.00000 10000.00| CLASS B CONCRETE, MODIFIED | | | 0400 601-03 1698.000 M3 | 700.00000 1188600.00| 900.00000 1528200.00| CLASS K CONCRETE | | | 0405 601-03(05) 260.000 M3 | 4100.00000 1066000.00| 2200.00000 572000.00| CLASS K CONCRETE BRIDGE RAILING | | | 0410 602-01 67596.000 KG | 1.50000 101394.00| 5.00000 337980.00| REIN STEEL BARS | | | 0415 602-02 273386.000 KG | 1.50000 410079.00| 2.50000 683465.00| EPOXY COATED REINFORCING BARS | | | 0420 615-03 1.000 LS | 400000.00000 400000.00| 700000.00000 700000.00| FABRICATED STRUCTURAL STEEL | | | 0425 625-19 34.000 M | 600.00000 20400.00| 1200.00000 40800.00| ELASTOMERIC CONCRETE STRIP SEAL | | | EXPANSION DAM | | | 0430 643-01 100.000 WK | 250.00000 25000.00| 350.00000 35000.00| PROGRESS PHOTOGRAPHS | | | 0435 643-02 12.000 EA | 250.00000 3000.00| 300.00000 3600.00| ADDITIONAL PHOTOGRAPHS, PER PHOTO FILED | | | TRIP | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -15 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(4) 47-0640263 |(5) 62-1345425 | |KIEWIT CONSTRUCTION COMPANY |BILCO CONSTRUCTION COMPANY, | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0440 679-06 LUMP| 3500.00000 3500.00| 3000.00000 3000.00| TEST SLAB | | | 0445 JB-1 4.000 EA | 18000.00000 72000.00| 16000.00000 64000.00| EAGLE FINIALS, FLAGPOLES AND FLAGPOLE | | | BASE LIGHTING | | | 0450 JB-2 LUMP| 70000.00000 70000.00| 75000.00000 75000.00| STANDARD STEEL DOORS, ALUMINUM WINDOWS | | | AND GLASS BLOCK | | | 0455 JB-5 100.000 M2 | 300.00000 30000.00| 1200.00000 120000.00| CLASS 1 CONCRETE REPAIRS | | | 0460 JB-6 30.000 M3 | 8500.00000 255000.00| 7500.00000 225000.00| CLASS 2 CONCRETE REPAIRS | | | 0465 JB-7 4000.000 M | 40.00000 160000.00| 20.00000 80000.00| CRACK REPAIRS | | | 0470 JB-9 LUMP| 740000.00000 740000.00| 2850000.00000 2850000.00| SUPPORT OF BELL ATLANTIC CABLES | | | 0475 679-02 BB1 163.000 M3 | | | LATEX MODIFIED PORTLAND CEMENT MORTAR | | | OR CONCRETE OVERLAYMENT OF BRIDGE DECK | | | 0480 679-04 BB2 163.000 M3 | 1000.00000 163000.00| 1100.00000 179300.00| MICROSILICA CONCRETE OVERLAY | | | SECTION TOTALS | $ 13,940,733.00| $ 13,484,215.00| ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0005 BRIDGE AND NAVIGATION LIGHTING | | | 0485 662-02 LUMP| 41000.00000 41000.00| 54200.00000 54200.00| GALVANIZED STEEL CONDUIT 662-021 | | | 0490 662-02 LUMP| 27000.00000 27000.00| 33000.00000 33000.00| GALVANIZED STEEL CONDUIT 662-022 | | | 0495 662-06L 56.000 EA | 640.00000 35840.00| 700.00000 39200.00| JUNCTION BOX | | | 0500 662-0750 104.000 EA | 2600.00000 270400.00| 2610.00000 271440.00| LUMINAIRES 50W HPS | | | 0505 662-10 40.000 EA | 3750.00000 150000.00| 6000.00000 240000.00| LIGHTING SUPPORT TYPE 6 | | | 0510 662-081 LUMP| 44000.00000 44000.00| 70000.00000 70000.00| CABLE | | | 0515 662-082 LUMP| 28000.00000 28000.00| 20500.00000 20500.00| CABLE | | | 0520 662-13 LUMP| 18550.00000 18550.00| 25000.00000 25000.00| SERVICE AND CONTROL STATION 662-131 | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -16 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(4) 47-0640263 |(5) 62-1345425 | |KIEWIT CONSTRUCTION COMPANY |BILCO CONSTRUCTION COMPANY, | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0525 662-13 LUMP| 13500.00000 13500.00| 21500.00000 21500.00| SERVICE AND CONTROL STATION 662-132 | | | 0530 662-14 LUMP| 6500.00000 6500.00| 15000.00000 15000.00| INCIDENTAL ELECTRICAL WORK | | | 0535 662-15 LUMP| 50.00000 50.00| 110.00000 110.00| ELECTRICAL TESTS 662-151 | | | 0540 662-15 LUMP| 50.00000 50.00| 110.00000 110.00| ELECTRICAL TESTS 662-152 | | | 0545 662-20 LUMP| 12000.00000 12000.00| 20000.00000 20000.00| NAVIGATION LIGHTING SYSTEM | | | SECTION TOTALS | $ 646,890.00| $ 810,060.00| ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0006 SPECIALITY ITEMS | | | 0550 603-18(710) 351.000 M | 300.00000 105300.00| 325.00000 114075.00| PRESTRESSED CONCRETE I BEAMS 710MM | | | 0555 603-18(915) 235.000 M | 350.00000 82250.00| 325.00000 76375.00| PRESTRESSED CONCRETE I BEAMS 915MM | | | 0560 603-20(150) 2848.000 M2 | 200.00000 569600.00| 195.00000 555360.00| PRESTRESSED CONCRETE DECK PANELS 150MM | | | 0565 603-20(250) 1163.000 M2 | 380.00000 441940.00| 375.00000 436125.00| PRESTRESSED CONCRETE DECK PANELS 250MM | | | 0570 603-21(250) 546.000 M2 | 500.00000 273000.00| 445.00000 242970.00| PRECAST CONCRETE DECK PANELS 250MM | | | 0575 603-22 433.000 M | 400.00000 173200.00| 565.00000 244645.00| PRECAST CONCRETE SPANDREL BEAMS | | | 0580 603-23 1825.000 M2 | 900.00000 1642500.00| 1350.00000 2463750.00| PRECAST CONCRETE RIB WALLS | | | 0585 603-24 894.000 M | 900.00000 804600.00| 1030.00000 920820.00| PRECAST CONCRETE CAP BEAMS | | | 0590 603-25 273.000 M2 | 1800.00000 491400.00| 1769.00000 482937.00| PRECAST ARCHITECTURAL CONCRETE | | | 0595 603-26 469.000 M | 495.00000 232155.00| 590.00000 276710.00| PRECAST CONCRETE - JB BEAMS | | | 0600 JB-3 370.000 M3 | 1900.00000 703000.00| 5000.00000 1850000.00| SHOTCRETE REPAIRS | | | 0605 JB-4 LUMP| 5000.00000 5000.00| 15000.00000 15000.00| SHOTCRETE TEST PANELS | | | 0610 JB-8 6400.000 M2 | 100.00000 640000.00| 104.00000 665600.00| SHOTCRETE OVERLAY | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 001 -17 TABULATION OF BIDS CALL ORDER : 001 CONTRACT ID : 9218030R1 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : Standard ==================================================================================================================================== |(4) 47-0640263 |(5) 62-1345425 | |KIEWIT CONSTRUCTION COMPANY |BILCO CONSTRUCTION COMPANY, | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0615 631-06(01) LUMP| 40000.00000 40000.00| 130000.00000 130000.00| RECTIFIER SYSTEM | | | 0620 631-06(02) 36.000 EA | 800.00000 28800.00| 250.00000 9000.00| REFERENCE CELL | | | 0625 631-06(03) 4734.000 M2 | 70.00000 331380.00| 75.00000 355050.00| ANODE SYSTEM | | | 0630 631-11 20.000 EA | 50.00000 1000.00| 85.00000 1700.00| CONTINUITY BONDS | | | 0635 631-12 LUMP| 55000.00000 55000.00| 82000.00000 82000.00| CORRISION ENGINEERING SERVICES | | | SECTION TOTALS | $ 6,620,125.00| $ 8,922,117.00| ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0007 COMPUTER SYSTEM | | | 0645 640-04 LUMP| 10000.00000 10000.00| 7500.00000 7500.00| COMPUTER SYSTEM FOR FIELD OFFICE | | | SECTION TOTALS | $ 10,000.00| $ 7,500.00| ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0008 TRAINING | | | 0650 699 3000.000 HR | 0.80000 2400.00| 0.80000 2400.00| ON JOB TRAINING | | | SECTION TOTALS | $ 2,400.00| $ 2,400.00| ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 23,023,913.00| $ 24,344,590.00| ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -1 VENDOR RANKING CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 CONTRACT DESCRIPTION : EL POCA TRUSS BRIDGE PROJECT(S) : S338-0219/00-019.53 00 PLBR 0219 039 E00 LOCATION: RTE 219 OVER STONY CREEK, 0.5 MI S CR 219/3 0 -------------------------------------------------------------------------------------------------------------------------- TOTAL % OVER RANK VENDOR NO./NAME BID LOW BID -------------------------------------------------------------------------------------------------------------------------- 1 55-0671461 HOKE BROTHERS CONTRACTING $ 723,741.24 100.0000% 2 55-0710073 TEAYS RIVER CONSTRUCTION COMPANY $ 785,391.88 108.5183% 3 55-0674033 SMH CONSTRUCTION CO., INC. $ 840,028.69 116.0675% 4 62-1345425 BILCO CONSTRUCTION COMPANY, INC. $ 857,197.00 118.4397% 5 55-0609442 MEC CONSTRUCTION, INC. $ 867,999.95 119.9323% 6 31-1316393 AHERN & ASSOCIATES, INC. $ 932,499.50 128.8443% 7 54-1161087 CORTE CONSTRUCTION CO., INC. & SUBSIDIARY $ 1,035,116.80 143.0230% 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -2 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(1) 55-0671461 |(2) 55-0710073 |(3) 55-0674033 |HOKE BROTHERS CONTRACTING |TEAYS RIVER CONSTRUCTION COM|SMH CONSTRUCTION CO., INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 1.000 LS | 5000.00000 5000.00| 36500.00000 36500.00| 8500.00000 8500.00 CLEARING AND GRUBBING | | | 0010 202-01 1.000 LS | 4000.00000 4000.00| 8500.00000 8500.00| 2300.00000 2300.00 BUILDING DEMOLITION 202-01(01) | | | 0015 202-01 1.000 LS | 4000.00000 4000.00| 7000.00000 7000.00| 5800.00000 5800.00 BUILDING DEMOLITION 202-01(02) | | | 0020 202-01 1.000 LS | 6000.00000 6000.00| 9000.00000 9000.00| 7000.00000 7000.00 BUILDING DEMOLITION 202-01(03) | | | 0025 202-01 1.000 LS | 4000.00000 4000.00| 4500.00000 4500.00| 2800.00000 2800.00 BUILDING DEMOLITION 202-01(04) | | | 0030 204-01 LUMP| 12000.00000 12000.00| 15000.00000 15000.00| 66000.00000 66000.00 MOBILIZATION | | | 0035 207-01 5996.000 M3 | 0.50000 2998.00| 5.00000 29980.00| 7.40000 44370.40 UNCLASSIFIED EXCAVATION | | | 0040 207-02 320.000 M3 | 30.00000 9600.00| 50.00000 16000.00| 32.20000 10304.00 SUBGRADE | | | 0045 207-34 2830.000 M2 | 2.00000 5660.00| 1.00000 2830.00| 1.10000 3113.00 FABRIC FOR SEPARATION | | | 0050 211-01 5709.000 M3 | 16.00000 91344.00| 8.00000 45672.00| 10.85000 61942.65 UNCLASSIFIED BORROW EXCAVATION | | | 0055 307-01 550.000 M3 | 30.00000 16500.00| 40.00000 22000.00| 30.30000 16665.00 CLASS I AGGREGATE BASE COURSE | | | 0060 308-01SG 575.000 MGR | 22.00000 12650.00| 15.00000 8625.00| 15.20000 8740.00 CLASS I AGGREGATE BASE COURSE, | | | STONE/GRAVEL | | | 0065 311-06 115.000 M3 | 69.70000 8015.50| 85.00000 9775.00| 158.40000 18216.00 OPEN GRADED FREE DRAINING BASE | | | 0070 408-02 194.000 L | 0.58000 112.52| 0.25000 48.50| 0.55000 106.70 BITUMINOUS MATERIAL | | | 0075 409-02 5715.000 L | 0.58000 3314.70| 0.25000 1428.75| 0.55000 3143.25 BITUMINOUS MATERIAL PRIME | | | 0080 501-01300 144.000 M2 | 125.00000 18000.00| 180.00000 25920.00| 154.65000 22269.60 REIN PORTLAND CEMENT CONCRETE PAVEMENT | | | 300MM | | | 0085 601-02 2.900 M3 | 1100.00000 3190.00| 1400.00000 4060.00| 1938.20000 5620.78 CLASS B CONCRETE | | | 0090 604-101025B2 23.000 M | 400.00000 9200.00| 250.00000 5750.00| 155.40000 3574.20 METALLIC COATED CORRUGATED STEEL PIPE | | | ARCHM 1225X825MM, A2 | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -3 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(1) 55-0671461 |(2) 55-0710073 |(3) 55-0674033 |HOKE BROTHERS CONTRACTING |TEAYS RIVER CONSTRUCTION COM|SMH CONSTRUCTION CO., INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0095 605-09 1.000 EA | 2200.00000 2200.00| 1000.00000 1000.00| 1829.00000 1829.00 TYPE G INLET | | | 0100 606-29 209.000 M | 25.00000 5225.00| 30.00000 6270.00| 34.85000 7283.65 FREE DRAINING BASE (FDB) TRENCH | | | 0105 606-30 43.000 M | 35.00000 1505.00| 85.00000 3655.00| 56.55000 2431.65 OUTLET PIPE | | | 0110 607-011 112.000 M | 80.30000 8993.60| 75.00000 8400.00| 82.30000 9217.60 TYPE 1 GUARDRAIL, CLASS I | | | 0115 607-28 4.000 EA | 825.00000 3300.00| 800.00000 3200.00| 845.75000 3383.00 MODIFIED ECCENTRIC LOADER TERMINAL | | | 0120 633-03 181.000 M3 | 30.00000 5430.00| 50.00000 9050.00| 33.80000 6117.80 DUMPED ROCK GUTTER | | | 0125 636-05 LUMP| 18000.00000 18000.00| 30000.00000 30000.00| 21500.00000 21500.00 TEMPORARY STRUCTURES FOR MAINTAINING | | | TRAFFIC | | | 0130 636-09 950.000 M | 5.00000 4750.00| 4.25000 4037.50| 4.85000 4607.50 TEMP PVMT MARKING-TAPE | | | 0135 636-11 9913.000 UN | 1.50000 14869.50| 0.01000 99.13| 0.01000 99.13 TRAFFIC CONTROL DEVICE | | | 0140 636-12 2.000 EA | 0.01000 0.02| 200.00000 400.00| 50.00000 100.00 CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0145 636-13 100.000 EA | 0.01000 1.00| 5.00000 500.00| 1.05000 105.00 CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0150 636-14 500.000 HR | 33.00000 16500.00| 0.01000 5.00| 34.55000 17275.00 FLAGGER | | | 0155 636-19 302.500 M | 40.70000 12311.75| 25.00000 7562.50| 36.20000 10950.50 TEMPORARY GUARDRAIL BARRIERS | | | 0160 636-25B 1440.000 DA | 2.50000 3600.00| 0.50000 720.00| 1.85000 2664.00 WARNING LIGHTS TYPE B | | | 0165 638-02 10.000 EA | 75.00000 750.00| 25.00000 250.00| 46.20000 462.00 RIGHT OF WAY MARKERS | | | 0170 639-01 LUMP| 4000.00000 4000.00| 2000.00000 2000.00| 7900.00000 7900.00 CONSTRUCTION LAYOUT STAKES | | | 0175 640-02 LUMP| 5000.00000 5000.00| 7000.00000 7000.00| 7350.00000 7350.00 SMALL FIELD OFFICE/STORAGE BUILDING | | | 0180 640-03 LUMP| 2000.00000 2000.00| 500.00000 500.00| 2200.00000 2200.00 BUILDING EQUIPMENT | | | 0185 642-14 LUMP| 800.00000 800.00| 500.00000 500.00| 3700.00000 3700.00 TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -4 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(1) 55-0671461 |(2) 55-0710073 |(3) 55-0674033 |HOKE BROTHERS CONTRACTING |TEAYS RIVER CONSTRUCTION COM|SMH CONSTRUCTION CO., INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0190 681-01 LUMP| 300.00000 300.00| 1000.00000 1000.00| 1130.00000 1130.00 ASBESTOS ABATEMENT 681-01(01) | | | 0195 681-01 LUMP| 33000.00000 33000.00| 33000.00000 33000.00| 50000.00000 50000.00 ASBESTOS ABATEMENT 681-01(03) | | | 0200 401-2(1)SG AA1 193.000 MGR | 76.00000 14668.00| 60.00000 11580.00| 74.60000 14397.80 HOT-MIX ASPHALT WEARING COURSE, STONE | | | OR GRAVEL | | | 0205 401-2(1)S AA2 176.000 MGR | | | HOT-MIX ASPHALT WEARING COURSE, SLAG | | | 0210 401-1(1)SG BB1 794.000 MGR | 76.00000 60344.00| 60.00000 47640.00| 74.60000 59232.40 HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0215 401-1(1)S BB2 724.000 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0220 604-040450A2 CC1 36.500 M | | | FULL BITUMINOUS COATED AND PAVED INVERT | | | CORRUGATED STEEL PIP E, 450MM, A2 | | | 0225 604-760450A2 CC2 36.500 M | 200.00000 7300.00| 125.00000 4562.50| 98.95000 3611.68 ALUMINUM COATED CORRUGATED STEEL PIPE, | | | 450MM, A2 | | | SECTION TOTALS | $ 440,432.59| $ 435,520.88| $ 528,013.29 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 BRIDGE #4180 | | | 0230 203-01 LUMP| 8000.00000 8000.00| 58000.00000 58000.00| 12200.00000 12200.00 DISMANTLING STRUCTURES | | | 0235 211-02 146.000 M3 | 32.00000 4672.00| 35.00000 5110.00| 35.05000 5117.30 ROCK BORROW EXCAVATION | | | 0240 212-01 40.000 M3 | 0.01000 0.40| 15.00000 600.00| 26.35000 1054.00 STRUCTURE EXCAVATION | | | 0245 212-05 61.000 M3 | 75.00000 4575.00| 50.00000 3050.00| 72.05000 4395.05 SELECT MATERIAL FOR BACKFILLING | | | 0250 601-02 60.000 M3 | 500.00000 30000.00| 550.00000 33000.00| 502.15000 30129.00 CLASS B CONCRETE | | | 0255 601-03 96.000 M3 | 540.00000 51840.00| 525.00000 50400.00| 696.50000 66864.00 CLASS K CONCRETE | | | 0260 602-02 8995.000 KG | 1.75000 15741.25| 2.00000 17990.00| 2.20000 19789.00 EPOXY COATED REINFORCING BARS | | | 0265 603-01 356.000 M | 370.00000 131720.00| 425.00000 151300.00| 378.90000 134888.40 PRESTRESSED CONCRETE BEAMS | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -5 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(1) 55-0671461 |(2) 55-0710073 |(3) 55-0674033 |HOKE BROTHERS CONTRACTING |TEAYS RIVER CONSTRUCTION COM|SMH CONSTRUCTION CO., INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0270 616-05H250062 117.000 M | 280.00000 32760.00| 260.00000 30420.00| 278.45000 32578.65 STEEL BEARING PILES, HP 250X62, | | | PRE-DRILLED AND DRIVEN | | | 0275 639-01 LUMP| 4000.00000 4000.00| 1.00000 1.00| 5000.00000 5000.00 CONSTRUCTION LAYOUT STAKES | | | SECTION TOTALS | $ 283,308.65| $ 349,871.00| $ 312,015.40 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 723,741.24| $ 785,391.88| $ 840,028.69 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -6 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(4) 62-1345425 |(5) 55-0609442 |(6) 31-1316393 |BILCO CONSTRUCTION COMPANY, |MEC CONSTRUCTION, INC. |AHERN & ASSOCIATES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 1.000 LS | 7000.00000 7000.00| 28000.00000 28000.00| 26624.55000 26624.55 CLEARING AND GRUBBING | | | 0010 202-01 1.000 LS | 800.00000 800.00| 3000.00000 3000.00| 6000.00000 6000.00 BUILDING DEMOLITION 202-01(01) | | | 0015 202-01 1.000 LS | 500.00000 500.00| 3000.00000 3000.00| 2000.00000 2000.00 BUILDING DEMOLITION 202-01(02) | | | 0020 202-01 1.000 LS | 800.00000 800.00| 3000.00000 3000.00| 10000.00000 10000.00 BUILDING DEMOLITION 202-01(03) | | | 0025 202-01 1.000 LS | 800.00000 800.00| 3000.00000 3000.00| 2000.00000 2000.00 BUILDING DEMOLITION 202-01(04) | | | 0030 204-01 LUMP| 30000.00000 30000.00| 22000.00000 22000.00| 34702.00000 34702.00 MOBILIZATION | | | 0035 207-01 5996.000 M3 | 10.00000 59960.00| 8.90000 53364.40| 6.50000 38974.00 UNCLASSIFIED EXCAVATION | | | 0040 207-02 320.000 M3 | 42.00000 13440.00| 50.00000 16000.00| 56.00000 17920.00 SUBGRADE | | | 0045 207-34 2830.000 M2 | 1.50000 4245.00| 1.40000 3962.00| 1.20000 3396.00 FABRIC FOR SEPARATION | | | 0050 211-01 5709.000 M3 | 12.00000 68508.00| 8.90000 50810.10| 10.50000 59944.50 UNCLASSIFIED BORROW EXCAVATION | | | 0055 307-01 550.000 M3 | 42.00000 23100.00| 50.00000 27500.00| 46.00000 25300.00 CLASS I AGGREGATE BASE COURSE | | | 0060 308-01SG 575.000 MGR | 24.00000 13800.00| 35.00000 20125.00| 16.50000 9487.50 CLASS I AGGREGATE BASE COURSE, | | | STONE/GRAVEL | | | 0065 311-06 115.000 M3 | 83.00000 9545.00| 73.00000 8395.00| 78.50000 9027.50 OPEN GRADED FREE DRAINING BASE | | | 0070 408-02 194.000 L | 0.50000 97.00| 0.55000 106.70| 0.55000 106.70 BITUMINOUS MATERIAL | | | 0075 409-02 5715.000 L | 0.30000 1714.50| 0.55000 3143.25| 0.55000 3143.25 BITUMINOUS MATERIAL PRIME | | | 0080 501-01300 144.000 M2 | 160.00000 23040.00| 175.00000 25200.00| 180.00000 25920.00 REIN PORTLAND CEMENT CONCRETE PAVEMENT | | | 300MM | | | 0085 601-02 2.900 M3 | 2000.00000 5800.00| 2000.00000 5800.00| 2200.00000 6380.00 CLASS B CONCRETE | | | 0090 604-101025B2 23.000 M | 740.00000 17020.00| 360.00000 8280.00| 250.00000 5750.00 METALLIC COATED CORRUGATED STEEL PIPE | | | ARCHM 1225X825MM, A2 | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -7 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(4) 62-1345425 |(5) 55-0609442 |(6) 31-1316393 |BILCO CONSTRUCTION COMPANY, |MEC CONSTRUCTION, INC. |AHERN & ASSOCIATES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0095 605-09 1.000 EA | 2200.00000 2200.00| 2200.00000 2200.00| 1200.00000 1200.00 TYPE G INLET | | | 0100 606-29 209.000 M | 30.00000 6270.00| 15.00000 3135.00| 25.00000 5225.00 FREE DRAINING BASE (FDB) TRENCH | | | 0105 606-30 43.000 M | 30.00000 1290.00| 10.00000 430.00| 80.00000 3440.00 OUTLET PIPE | | | 0110 607-011 112.000 M | 80.00000 8960.00| 70.00000 7840.00| 82.00000 9184.00 TYPE 1 GUARDRAIL, CLASS I | | | 0115 607-28 4.000 EA | 825.00000 3300.00| 825.00000 3300.00| 815.00000 3260.00 MODIFIED ECCENTRIC LOADER TERMINAL | | | 0120 633-03 181.000 M3 | 59.00000 10679.00| 48.00000 8688.00| 40.00000 7240.00 DUMPED ROCK GUTTER | | | 0125 636-05 LUMP| 90000.00000 90000.00| 35000.00000 35000.00| 50000.00000 50000.00 TEMPORARY STRUCTURES FOR MAINTAINING | | | TRAFFIC | | | 0130 636-09 950.000 M | 5.00000 4750.00| 4.70000 4465.00| 4.50000 4275.00 TEMP PVMT MARKING-TAPE | | | 0135 636-11 9913.000 UN | 1.00000 9913.00| 1.50000 14869.50| 1.50000 14869.50 TRAFFIC CONTROL DEVICE | | | 0140 636-12 2.000 EA | 0.50000 1.00| 330.00000 660.00| 450.00000 900.00 CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0145 636-13 100.000 EA | 0.01000 1.00| 5.50000 550.00| 4.50000 450.00 CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0150 636-14 500.000 HR | 33.00000 16500.00| 35.00000 17500.00| 35.00000 17500.00 FLAGGER | | | 0155 636-19 302.500 M | 38.00000 11495.00| 46.00000 13915.00| 40.00000 12100.00 TEMPORARY GUARDRAIL BARRIERS | | | 0160 636-25B 1440.000 DA | 2.50000 3600.00| 2.25000 3240.00| 2.35000 3384.00 WARNING LIGHTS TYPE B | | | 0165 638-02 10.000 EA | 125.00000 1250.00| 100.00000 1000.00| 50.00000 500.00 RIGHT OF WAY MARKERS | | | 0170 639-01 LUMP| 3500.50000 3500.50| 5000.00000 5000.00| 9000.00000 9000.00 CONSTRUCTION LAYOUT STAKES | | | 0175 640-02 LUMP| 7000.00000 7000.00| 8000.00000 8000.00| 6000.00000 6000.00 SMALL FIELD OFFICE/STORAGE BUILDING | | | 0180 640-03 LUMP| 1500.00000 1500.00| 3500.00000 3500.00| 1700.00000 1700.00 BUILDING EQUIPMENT | | | 0185 642-14 LUMP| 1500.00000 1500.00| 2000.00000 2000.00| 2500.00000 2500.00 TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -8 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(4) 62-1345425 |(5) 55-0609442 |(6) 31-1316393 |BILCO CONSTRUCTION COMPANY, |MEC CONSTRUCTION, INC. |AHERN & ASSOCIATES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0190 681-01 LUMP| 500.00000 500.00| 6000.00000 6000.00| 500.00000 500.00 ASBESTOS ABATEMENT 681-01(01) | | | 0195 681-01 LUMP| 30000.00000 30000.00| 23000.00000 23000.00| 31000.00000 31000.00 ASBESTOS ABATEMENT 681-01(03) | | | 0200 401-2(1)SG AA1 193.000 MGR | 58.00000 11194.00| 73.00000 14089.00| 72.00000 13896.00 HOT-MIX ASPHALT WEARING COURSE, STONE | | | OR GRAVEL | | | 0205 401-2(1)S AA2 176.000 MGR | | | HOT-MIX ASPHALT WEARING COURSE, SLAG | | | 0210 401-1(1)SG BB1 794.000 MGR | 58.00000 46052.00| 73.00000 57962.00| 72.00000 57168.00 HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0215 401-1(1)S BB2 724.000 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0220 604-040450A2 CC1 36.500 M | | | FULL BITUMINOUS COATED AND PAVED INVERT | | | CORRUGATED STEEL PIP E, 450MM, A2 | | | 0225 604-760450A2 CC2 36.500 M | 150.00000 5475.00| 125.00000 4562.50| 82.00000 2993.00 ALUMINUM COATED CORRUGATED STEEL PIPE, | | | 450MM, A2 | | | SECTION TOTALS | $ 557,100.00| $ 525,592.45| $ 544,960.50 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 BRIDGE #4180 | | | 0230 203-01 LUMP| 32000.00000 32000.00| 26616.50000 26616.50| 45000.00000 45000.00 DISMANTLING STRUCTURES | | | 0235 211-02 146.000 M3 | 52.00000 7592.00| 50.00000 7300.00| 45.00000 6570.00 ROCK BORROW EXCAVATION | | | 0240 212-01 40.000 M3 | 46.00000 1840.00| 30.00000 1200.00| 47.00000 1880.00 STRUCTURE EXCAVATION | | | 0245 212-05 61.000 M3 | 90.00000 5490.00| 120.00000 7320.00| 90.00000 5490.00 SELECT MATERIAL FOR BACKFILLING | | | 0250 601-02 60.000 M3 | 455.00000 27300.00| 550.00000 33000.00| 585.00000 35100.00 CLASS B CONCRETE | | | 0255 601-03 96.000 M3 | 455.00000 43680.00| 600.00000 57600.00| 785.00000 75360.00 CLASS K CONCRETE | | | 0260 602-02 8995.000 KG | 2.00000 17990.00| 1.80000 16191.00| 2.20000 19789.00 EPOXY COATED REINFORCING BARS | | | 0265 603-01 356.000 M | 400.00000 142400.00| 430.00000 153080.00| 445.00000 158420.00 PRESTRESSED CONCRETE BEAMS | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -9 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(4) 62-1345425 |(5) 55-0609442 |(6) 31-1316393 |BILCO CONSTRUCTION COMPANY, |MEC CONSTRUCTION, INC. |AHERN & ASSOCIATES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0270 616-05H250062 117.000 M | 165.00000 19305.00| 300.00000 35100.00| 290.00000 33930.00 STEEL BEARING PILES, HP 250X62, | | | PRE-DRILLED AND DRIVEN | | | 0275 639-01 LUMP| 2500.00000 2500.00| 5000.00000 5000.00| 6000.00000 6000.00 CONSTRUCTION LAYOUT STAKES | | | SECTION TOTALS | $ 300,097.00| $ 342,407.50| $ 387,539.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 857,197.00| $ 867,999.95| $ 932,499.50 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -10 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(7) 54-1161087 | | |CORTE CONSTRUCTION CO., INC.| | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 1.000 LS | 20000.00000 20000.00| | CLEARING AND GRUBBING | | | 0010 202-01 1.000 LS | 7000.00000 7000.00| | BUILDING DEMOLITION 202-01(01) | | | 0015 202-01 1.000 LS | 6000.00000 6000.00| | BUILDING DEMOLITION 202-01(02) | | | 0020 202-01 1.000 LS | 8000.00000 8000.00| | BUILDING DEMOLITION 202-01(03) | | | 0025 202-01 1.000 LS | 3000.00000 3000.00| | BUILDING DEMOLITION 202-01(04) | | | 0030 204-01 LUMP| 20000.00000 20000.00| | MOBILIZATION | | | 0035 207-01 5996.000 M3 | 8.00000 47968.00| | UNCLASSIFIED EXCAVATION | | | 0040 207-02 320.000 M3 | 60.00000 19200.00| | SUBGRADE | | | 0045 207-34 2830.000 M2 | 2.00000 5660.00| | FABRIC FOR SEPARATION | | | 0050 211-01 5709.000 M3 | 10.00000 57090.00| | UNCLASSIFIED BORROW EXCAVATION | | | 0055 307-01 550.000 M3 | 50.00000 27500.00| | CLASS I AGGREGATE BASE COURSE | | | 0060 308-01SG 575.000 MGR | 30.00000 17250.00| | CLASS I AGGREGATE BASE COURSE, | | | STONE/GRAVEL | | | 0065 311-06 115.000 M3 | 135.00000 15525.00| | OPEN GRADED FREE DRAINING BASE | | | 0070 408-02 194.000 L | 0.30000 58.20| | BITUMINOUS MATERIAL | | | 0075 409-02 5715.000 L | 0.30000 1714.50| | BITUMINOUS MATERIAL PRIME | | | 0080 501-01300 144.000 M2 | 160.00000 23040.00| | REIN PORTLAND CEMENT CONCRETE PAVEMENT | | | 300MM | | | 0085 601-02 2.900 M3 | 1250.00000 3625.00| | CLASS B CONCRETE | | | 0090 604-101025B2 23.000 M | 200.00000 4600.00| | METALLIC COATED CORRUGATED STEEL PIPE | | | ARCHM 1225X825MM, A2 | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -11 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(7) 54-1161087 | | |CORTE CONSTRUCTION CO., INC.| | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0095 605-09 1.000 EA | 3000.00000 3000.00| | TYPE G INLET | | | 0100 606-29 209.000 M | 24.00000 5016.00| | FREE DRAINING BASE (FDB) TRENCH | | | 0105 606-30 43.000 M | 20.00000 860.00| | OUTLET PIPE | | | 0110 607-011 112.000 M | 85.00000 9520.00| | TYPE 1 GUARDRAIL, CLASS I | | | 0115 607-28 4.000 EA | 875.00000 3500.00| | MODIFIED ECCENTRIC LOADER TERMINAL | | | 0120 633-03 181.000 M3 | 45.00000 8145.00| | DUMPED ROCK GUTTER | | | 0125 636-05 LUMP| 145000.00000 145000.00| | TEMPORARY STRUCTURES FOR MAINTAINING | | | TRAFFIC | | | 0130 636-09 950.000 M | 5.00000 4750.00| | TEMP PVMT MARKING-TAPE | | | 0135 636-11 9913.000 UN | 1.20000 11895.60| | TRAFFIC CONTROL DEVICE | | | 0140 636-12 2.000 EA | 320.00000 640.00| | CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0145 636-13 100.000 EA | 3.25000 325.00| | CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0150 636-14 500.000 HR | 25.00000 12500.00| | FLAGGER | | | 0155 636-19 302.500 M | 50.00000 15125.00| | TEMPORARY GUARDRAIL BARRIERS | | | 0160 636-25B 1440.000 DA | 1.80000 2592.00| | WARNING LIGHTS TYPE B | | | 0165 638-02 10.000 EA | 90.00000 900.00| | RIGHT OF WAY MARKERS | | | 0170 639-01 LUMP| 3000.00000 3000.00| | CONSTRUCTION LAYOUT STAKES | | | 0175 640-02 LUMP| 12000.00000 12000.00| | SMALL FIELD OFFICE/STORAGE BUILDING | | | 0180 640-03 LUMP| 3000.00000 3000.00| | BUILDING EQUIPMENT | | | 0185 642-14 LUMP| 6000.00000 6000.00| | TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -12 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(7) 54-1161087 | | |CORTE CONSTRUCTION CO., INC.| | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0190 681-01 LUMP| 1500.00000 1500.00| | ASBESTOS ABATEMENT 681-01(01) | | | 0195 681-01 LUMP| 70000.00000 70000.00| | ASBESTOS ABATEMENT 681-01(03) | | | 0200 401-2(1)SG AA1 193.000 MGR | 55.00000 10615.00| | HOT-MIX ASPHALT WEARING COURSE, STONE | | | OR GRAVEL | | | 0205 401-2(1)S AA2 176.000 MGR | | | HOT-MIX ASPHALT WEARING COURSE, SLAG | | | 0210 401-1(1)SG BB1 794.000 MGR | 55.00000 43670.00| | HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0215 401-1(1)S BB2 724.000 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0220 604-040450A2 CC1 36.500 M | | | FULL BITUMINOUS COATED AND PAVED INVERT | | | CORRUGATED STEEL PIP E, 450MM, A2 | | | 0225 604-760450A2 CC2 36.500 M | 95.00000 3467.50| | ALUMINUM COATED CORRUGATED STEEL PIPE, | | | 450MM, A2 | | | SECTION TOTALS | $ 664,251.80| | ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 BRIDGE #4180 | | | 0230 203-01 LUMP| 50000.00000 50000.00| | DISMANTLING STRUCTURES | | | 0235 211-02 146.000 M3 | 60.00000 8760.00| | ROCK BORROW EXCAVATION | | | 0240 212-01 40.000 M3 | 55.00000 2200.00| | STRUCTURE EXCAVATION | | | 0245 212-05 61.000 M3 | 65.00000 3965.00| | SELECT MATERIAL FOR BACKFILLING | | | 0250 601-02 60.000 M3 | 575.00000 34500.00| | CLASS B CONCRETE | | | 0255 601-03 96.000 M3 | 675.00000 64800.00| | CLASS K CONCRETE | | | 0260 602-02 8995.000 KG | 2.00000 17990.00| | EPOXY COATED REINFORCING BARS | | | 0265 603-01 356.000 M | 475.00000 169100.00| | PRESTRESSED CONCRETE BEAMS | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 002 -13 TABULATION OF BIDS CALL ORDER : 002 CONTRACT ID : 9218149 COUNTIES : POCAHONTAS LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 08 SET-ASIDE : ==================================================================================================================================== |(7) 54-1161087 | | |CORTE CONSTRUCTION CO., INC.| | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0270 616-05H250062 117.000 M | 150.00000 17550.00| | STEEL BEARING PILES, HP 250X62, | | | PRE-DRILLED AND DRIVEN | | | 0275 639-01 LUMP| 2000.00000 2000.00| | CONSTRUCTION LAYOUT STAKES | | | SECTION TOTALS | $ 370,865.00| | ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 1,035,116.80| | ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 003 -1 VENDOR RANKING CALL ORDER : 003 CONTRACT ID : 9416002 COUNTIES : PUTNAM LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 01 CONTRACT DESCRIPTION : LITTLE HURRICANE CREEK BRIDGE PROJECT(S) : S340-0034/00-019.87 00 00BH 0034 034 LOCATION: 0.29 M S I/S US RTE 35 0 -------------------------------------------------------------------------------------------------------------------------- TOTAL % OVER RANK VENDOR NO./NAME BID LOW BID -------------------------------------------------------------------------------------------------------------------------- 1 62-1345425 BILCO CONSTRUCTION COMPANY, INC. $ 798,705.00 100.0000% 2 55-0487806 ORDERS CONSTRUCTION COMPANY, INC. $ 817,593.44 102.3648% 3 55-0417282 TURMAN CONSTRUCTION CO. $ 886,609.40 111.0058% 4 39-0884623 EDWARD KRAEMER & SONS, INC. $ 921,203.00 115.3370% 5 55-0534372 M & H CONCRETE STRUCTURES, INC. $ 928,701.23 116.2758% 6 31-1316393 AHERN & ASSOCIATES, INC. $ 934,000.00 116.9392% 7 55-0710073 TEAYS RIVER CONSTRUCTION COMPANY $ 1,139,000.00 142.6058% 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 003 -2 TABULATION OF BIDS CALL ORDER : 003 CONTRACT ID : 9416002 COUNTIES : PUTNAM LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 01 SET-ASIDE : ==================================================================================================================================== |(1) 62-1345425 |(2) 55-0487806 |(3) 55-0417282 |BILCO CONSTRUCTION COMPANY, |ORDERS CONSTRUCTION COMPANY,|TURMAN CONSTRUCTION CO. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 1.000 LS | 30900.00000 30900.00| 38000.00000 38000.00| 20000.00000 20000.00 CLEARING AND GRUBBING | | | 0010 204-01 LUMP| 31000.00000 31000.00| 19300.00000 19300.00| 21000.00000 21000.00 MOBILIZATION | | | 0015 207-01 81.000 M3 | 20.00000 1620.00| 38.50000 3118.50| 22.00000 1782.00 UNCLASSIFIED EXCAVATION | | | 0020 207-02 4.000 M3 | 50.00000 200.00| 62.50000 250.00| 70.00000 280.00 SUBGRADE | | | 0025 211-01 4226.000 M3 | 13.00000 54938.00| 17.40000 73532.40| 22.00000 92972.00 UNCLASSIFIED BORROW EXCAVATION | | | 0030 211-02 40.000 M3 | 59.00000 2360.00| 100.00000 4000.00| 100.00000 4000.00 ROCK BORROW EXCAVATION | | | 0035 307-01 184.000 M3 | 50.00000 9200.00| 62.50000 11500.00| 50.00000 9200.00 CLASS I AGGREGATE BASE COURSE | | | 0040 308-01 18.000 MGR | 30.00000 540.00| 40.00000 720.00| 35.00000 630.00 CLASS 1 AGGREGATE BASE COURSE | | | 0045 408-02 72.000 L | 0.50000 36.00| 0.22000 15.84| 0.20000 14.40 BITUMINOUS MATERIAL | | | 0050 409-02 1592.000 L | 0.25000 398.00| 0.22000 350.24| 0.20000 318.40 BITUMINOUS MATERIAL PRIME | | | 0055 502-01300 130.000 M2 | 168.00000 21840.00| 212.00000 27560.00| 150.00000 19500.00 PORTLAND CEMENT CONCRETE APPRACH SLAB | | | 300MM | | | 0060 607-011 161.700 M | 60.00000 9702.00| 61.60000 9960.72| 56.00000 9055.20 TYPE 1 GUARDRAIL, CLASS I | | | 0065 607-012 120.000 M | 45.00000 5400.00| 43.35000 5202.00| 39.40000 4728.00 TYPE 1 GUARDRAIL CLASS II | | | 0070 607-101 286.000 M | 5.50000 1573.00| 5.50000 1573.00| 5.00000 1430.00 TYPE 1 GUARDRAIL REMOVED AND STORED | | | 0075 607-28 2.000 EA | 880.00000 1760.00| 880.00000 1760.00| 800.00000 1600.00 MODIFIED ECCENTRIC LOADER TERMINAL | | | 0080 636-07 400.000 M | 3.25000 1300.00| 1.65000 660.00| 1.50000 600.00 ERADICATION PAVEMENT MARKINGS | | | 0085 636-08 880.000 M | 1.75000 1540.00| 1.10000 968.00| 1.00000 880.00 TEMP PVMT MARKING-PAINT | | | 0090 636-09 808.000 M | 5.00000 4040.00| 4.50000 3636.00| 4.10000 3312.80 TEMP PVMT MARKING-TAPE | | | 0095 636-11 9030.000 UN | 1.00000 9030.00| 1.39000 12551.70| 1.26000 11377.80 TRAFFIC CONTROL DEVICE | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 003 -3 TABULATION OF BIDS CALL ORDER : 003 CONTRACT ID : 9416002 COUNTIES : PUTNAM LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 01 SET-ASIDE : ==================================================================================================================================== |(1) 62-1345425 |(2) 55-0487806 |(3) 55-0417282 |BILCO CONSTRUCTION COMPANY, |ORDERS CONSTRUCTION COMPANY,|TURMAN CONSTRUCTION CO. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0100 636-12 5.000 EA | 0.20000 1.00| 110.00000 550.00| 100.00000 500.00 CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0105 636-13 50.000 EA | 0.02000 1.00| 1.10000 55.00| 1.00000 50.00 CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0110 636-14 1000.000 HR | 0.01000 10.00| 0.01000 10.00| 30.00000 30000.00 FLAGGER | | | 0115 636-25A 1200.000 DA | 0.01000 12.00| 0.50000 600.00| 0.45000 540.00 WARNING LIGHTS TYPE A | | | 0120 636-25B 2500.000 DA | 0.01000 25.00| 1.10000 2750.00| 1.00000 2500.00 WARNING LIGHTS TYPE B | | | 0125 639-01 LUMP| 3500.00000 3500.00| 5000.00000 5000.00| 4500.00000 4500.00 CONSTRUCTION LAYOUT STAKES | | | 0130 640-02 LUMP| 6750.00000 6750.00| 8400.00000 8400.00| 7500.00000 7500.00 SMALL FIELD OFFICE/STORAGE BUILDING | | | 0135 640-03 LUMP| 2000.00000 2000.00| 1000.00000 1000.00| 1500.00000 1500.00 BUILDING EQUIPMENT | | | 0140 642-14 LUMP| 1500.00000 1500.00| 3000.00000 3000.00| 1500.00000 1500.00 TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 0145 401-1(1)SG AA1 170.000 MGR | 60.00000 10200.00| 60.50000 10285.00| 55.00000 9350.00 HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0150 401-1(1)S AA2 155.000 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0155 401-2(1)S AB2 16.000 MGR | | | HOT-MIX ASPHALT WEARING COURSE, SLAG | | | 0160 401-2(1)SG AB1 18.000 MGR | 100.00000 1800.00| 104.50000 1881.00| 95.00000 1710.00 HOT-MIX ASPHALT WEARING COURSE, STONE | | | OR GRAVEL | | | 0165 401-3SG AC1 19.000 MGR | 100.00000 1900.00| 104.50000 1985.50| 95.00000 1805.00 HOT-MIX ASPHALT PATCH AND LEVEL COURSE, | | | STONE OR GRAVEL | | | 0170 401-3S AC2 17.000 MGR | | | HOT-MIX ASPHALT PATCH AND LEVEL COURSE, | | | SLAG | | | 0175 402-01SG AD1 87.000 MGR | 100.00000 8700.00| 104.50000 9091.50| 95.00000 8265.00 HMA SKID PAVEMENT, STONE/GRAVEL | | | 0180 402-01S AD2 78.000 MGR | | | HMA SKID PAVEMENT, SLAG | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 003 -4 TABULATION OF BIDS CALL ORDER : 003 CONTRACT ID : 9416002 COUNTIES : PUTNAM LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 01 SET-ASIDE : ==================================================================================================================================== |(1) 62-1345425 |(2) 55-0487806 |(3) 55-0417282 |BILCO CONSTRUCTION COMPANY, |ORDERS CONSTRUCTION COMPANY,|TURMAN CONSTRUCTION CO. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0185 636-02SG AE1 16.000 MGR | 30.00000 480.00| 25.00000 400.00| 30.00000 480.00 AGGREGATE FOR MAINTAINING TRAFFIC, | | | STONE OR GRAVEL | | | 0190 636-02S AE2 15.000 MGR | | | AGGREGATE FOR MAINTAINING TRAFFIC, SLAG | | | SECTION TOTALS | $ 224,256.00| $ 259,666.40| $ 272,880.60 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 BRIDGE #1813 | | | 0195 203-01 LUMP| 53200.00000 53200.00| 66000.00000 66000.00| 57500.00000 57500.00 DISMANTLING STRUCTURES | | | 0200 212-01 15.000 M3 | 90.00000 1350.00| 92.00000 1380.00| 50.00000 750.00 STRUCTURE EXCAVATION | | | 0205 212-05 15.000 M3 | 100.00000 1500.00| 110.00000 1650.00| 70.00000 1050.00 SELECT MATERIAL FOR BACKFILLING | | | 0210 601-02 54.000 M3 | 780.00000 42120.00| 1140.00000 61560.00| 1250.00000 67500.00 CLASS B CONCRETE | | | 0215 601-03 181.000 M3 | 585.00000 105885.00| 795.00000 143895.00| 650.00000 117650.00 CLASS K CONCRETE | | | 0220 602-01 2484.000 KG | 2.00000 4968.00| 1.41000 3502.44| 1.50000 3726.00 REIN STEEL BARS | | | 0225 602-02 30232.000 KG | 1.75000 52906.00| 1.55000 46859.60| 1.65000 49882.80 EPOXY COATED REINFORCING BARS | | | 0230 606-250150 26.000 M | 20.00000 520.00| 30.00000 780.00| 45.00000 1170.00 UNDERDRAIN PIPE 150MM | | | 0235 615-01 1.000 LS | 185000.00000 185000.00| 131000.00000 131000.00| 155000.00000 155000.00 STEEL SUPERSTRUCTURE | | | 0240 636-05 LUMP| 124000.00000 124000.00| 95000.00000 95000.00| 155000.00000 155000.00 TEMPORARY STRUCTURES FOR MAINTAINING | | | TRAFFIC | | | 0245 639-01 LUMP| 3000.00000 3000.00| 6300.00000 6300.00| 4500.00000 4500.00 CONSTRUCTION LAYOUT STAKES | | | SECTION TOTALS | $ 574,449.00| $ 557,927.04| $ 613,728.80 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 798,705.00| $ 817,593.44| $ 886,609.40 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 003 -5 TABULATION OF BIDS CALL ORDER : 003 CONTRACT ID : 9416002 COUNTIES : PUTNAM LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 01 SET-ASIDE : ==================================================================================================================================== |(4) 39-0884623 |(5) 55-0534372 |(6) 31-1316393 |EDWARD KRAEMER & SONS, INC. |M & H CONCRETE STRUCTURES, I|AHERN & ASSOCIATES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 1.000 LS | 5500.00000 5500.00| 28000.00000 28000.00| 4000.00000 4000.00 CLEARING AND GRUBBING | | | 0010 204-01 LUMP| 17200.00000 17200.00| 32000.00000 32000.00| 30000.00000 30000.00 MOBILIZATION | | | 0015 207-01 81.000 M3 | 20.00000 1620.00| 24.00000 1944.00| 15.00000 1215.00 UNCLASSIFIED EXCAVATION | | | 0020 207-02 4.000 M3 | 100.00000 400.00| 100.00000 400.00| 70.00000 280.00 SUBGRADE | | | 0025 211-01 4226.000 M3 | 26.00000 109876.00| 26.00000 109876.00| 15.00000 63390.00 UNCLASSIFIED BORROW EXCAVATION | | | 0030 211-02 40.000 M3 | 50.00000 2000.00| 71.20000 2848.00| 90.00000 3600.00 ROCK BORROW EXCAVATION | | | 0035 307-01 184.000 M3 | 35.00000 6440.00| 56.50000 10396.00| 70.00000 12880.00 CLASS I AGGREGATE BASE COURSE | | | 0040 308-01 18.000 MGR | 50.00000 900.00| 65.00000 1170.00| 70.00000 1260.00 CLASS 1 AGGREGATE BASE COURSE | | | 0045 408-02 72.000 L | 0.20000 14.40| 0.22000 15.84| 0.20000 14.40 BITUMINOUS MATERIAL | | | 0050 409-02 1592.000 L | 0.20000 318.40| 0.22000 350.24| 0.20000 318.40 BITUMINOUS MATERIAL PRIME | | | 0055 502-01300 130.000 M2 | 140.00000 18200.00| 165.00000 21450.00| 250.00000 32500.00 PORTLAND CEMENT CONCRETE APPRACH SLAB | | | 300MM | | | 0060 607-011 161.700 M | 56.00000 9055.20| 70.50000 11399.85| 56.00000 9055.20 TYPE 1 GUARDRAIL, CLASS I | | | 0065 607-012 120.000 M | 39.40000 4728.00| 52.00000 6240.00| 39.40000 4728.00 TYPE 1 GUARDRAIL CLASS II | | | 0070 607-101 286.000 M | 5.00000 1430.00| 3.50000 1001.00| 5.00000 1430.00 TYPE 1 GUARDRAIL REMOVED AND STORED | | | 0075 607-28 2.000 EA | 800.00000 1600.00| 825.00000 1650.00| 800.00000 1600.00 MODIFIED ECCENTRIC LOADER TERMINAL | | | 0080 636-07 400.000 M | 1.50000 600.00| 3.00000 1200.00| 1.50000 600.00 ERADICATION PAVEMENT MARKINGS | | | 0085 636-08 880.000 M | 1.00000 880.00| 2.25000 1980.00| 1.00000 880.00 TEMP PVMT MARKING-PAINT | | | 0090 636-09 808.000 M | 4.10000 3312.80| 4.00000 3232.00| 4.10000 3312.80 TEMP PVMT MARKING-TAPE | | | 0095 636-11 9030.000 UN | 1.26000 11377.80| 1.25000 11287.50| 1.26000 11377.80 TRAFFIC CONTROL DEVICE | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 003 -6 TABULATION OF BIDS CALL ORDER : 003 CONTRACT ID : 9416002 COUNTIES : PUTNAM LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 01 SET-ASIDE : ==================================================================================================================================== |(4) 39-0884623 |(5) 55-0534372 |(6) 31-1316393 |EDWARD KRAEMER & SONS, INC. |M & H CONCRETE STRUCTURES, I|AHERN & ASSOCIATES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0100 636-12 5.000 EA | 100.00000 500.00| 10.00000 50.00| 100.00000 500.00 CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0105 636-13 50.000 EA | 1.00000 50.00| 4.00000 200.00| 1.00000 50.00 CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0110 636-14 1000.000 HR | 37.00000 37000.00| 32.00000 32000.00| 18.00000 18000.00 FLAGGER | | | 0115 636-25A 1200.000 DA | 0.45000 540.00| 0.65000 780.00| 0.45000 540.00 WARNING LIGHTS TYPE A | | | 0120 636-25B 2500.000 DA | 1.00000 2500.00| 2.00000 5000.00| 1.00000 2500.00 WARNING LIGHTS TYPE B | | | 0125 639-01 LUMP| 20000.00000 20000.00| 3000.00000 3000.00| 3000.00000 3000.00 CONSTRUCTION LAYOUT STAKES | | | 0130 640-02 LUMP| 20000.00000 20000.00| 8000.00000 8000.00| 15000.00000 15000.00 SMALL FIELD OFFICE/STORAGE BUILDING | | | 0135 640-03 LUMP| 10000.00000 10000.00| 4000.00000 4000.00| 3000.00000 3000.00 BUILDING EQUIPMENT | | | 0140 642-14 LUMP| 10000.00000 10000.00| 4000.00000 4000.00| 3000.00000 3000.00 TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 0145 401-1(1)SG AA1 170.000 MGR | 55.00000 9350.00| 60.50000 10285.00| 55.00000 9350.00 HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0150 401-1(1)S AA2 155.000 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0155 401-2(1)S AB2 16.000 MGR | | | HOT-MIX ASPHALT WEARING COURSE, SLAG | | | 0160 401-2(1)SG AB1 18.000 MGR | 95.00000 1710.00| 105.00000 1890.00| 95.00000 1710.00 HOT-MIX ASPHALT WEARING COURSE, STONE | | | OR GRAVEL | | | 0165 401-3SG AC1 19.000 MGR | 95.00000 1805.00| 105.00000 1995.00| 95.00000 1805.00 HOT-MIX ASPHALT PATCH AND LEVEL COURSE, | | | STONE OR GRAVEL | | | 0170 401-3S AC2 17.000 MGR | | | HOT-MIX ASPHALT PATCH AND LEVEL COURSE, | | | SLAG | | | 0175 402-01SG AD1 87.000 MGR | 95.00000 8265.00| 105.00000 9135.00| 95.00000 8265.00 HMA SKID PAVEMENT, STONE/GRAVEL | | | 0180 402-01S AD2 78.000 MGR | | | HMA SKID PAVEMENT, SLAG | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 003 -7 TABULATION OF BIDS CALL ORDER : 003 CONTRACT ID : 9416002 COUNTIES : PUTNAM LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 01 SET-ASIDE : ==================================================================================================================================== |(4) 39-0884623 |(5) 55-0534372 |(6) 31-1316393 |EDWARD KRAEMER & SONS, INC. |M & H CONCRETE STRUCTURES, I|AHERN & ASSOCIATES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0185 636-02SG AE1 16.000 MGR | 50.00000 800.00| 22.00000 352.00| 25.00000 400.00 AGGREGATE FOR MAINTAINING TRAFFIC, | | | STONE OR GRAVEL | | | 0190 636-02S AE2 15.000 MGR | | | AGGREGATE FOR MAINTAINING TRAFFIC, SLAG | | | SECTION TOTALS | $ 317,972.60| $ 327,127.43| $ 249,561.60 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 BRIDGE #1813 | | | 0195 203-01 LUMP| 96500.00000 96500.00| 85320.00000 85320.00| 96549.20000 96549.20 DISMANTLING STRUCTURES | | | 0200 212-01 15.000 M3 | 80.00000 1200.00| 20.00000 300.00| 120.00000 1800.00 STRUCTURE EXCAVATION | | | 0205 212-05 15.000 M3 | 80.00000 1200.00| 90.00000 1350.00| 130.00000 1950.00 SELECT MATERIAL FOR BACKFILLING | | | 0210 601-02 54.000 M3 | 1200.00000 64800.00| 585.00000 31590.00| 755.00000 40770.00 CLASS B CONCRETE | | | 0215 601-03 181.000 M3 | 500.00000 90500.00| 675.00000 122175.00| 850.00000 153850.00 CLASS K CONCRETE | | | 0220 602-01 2484.000 KG | 1.50000 3726.00| 1.75000 4347.00| 1.20000 2980.80 REIN STEEL BARS | | | 0225 602-02 30232.000 KG | 1.70000 51394.40| 1.65000 49882.80| 1.20000 36278.40 EPOXY COATED REINFORCING BARS | | | 0230 606-250150 26.000 M | 35.00000 910.00| 9.00000 234.00| 60.00000 1560.00 UNDERDRAIN PIPE 150MM | | | 0235 615-01 1.000 LS | 123000.00000 123000.00| 165525.00000 165525.00| 143200.00000 143200.00 STEEL SUPERSTRUCTURE | | | 0240 636-05 LUMP| 150000.00000 150000.00| 136850.00000 136850.00| 200000.00000 200000.00 TEMPORARY STRUCTURES FOR MAINTAINING | | | TRAFFIC | | | 0245 639-01 LUMP| 20000.00000 20000.00| 4000.00000 4000.00| 5500.00000 5500.00 CONSTRUCTION LAYOUT STAKES | | | SECTION TOTALS | $ 603,230.40| $ 601,573.80| $ 684,438.40 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 921,203.00| $ 928,701.23| $ 934,000.00 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 003 -8 TABULATION OF BIDS CALL ORDER : 003 CONTRACT ID : 9416002 COUNTIES : PUTNAM LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 01 SET-ASIDE : ==================================================================================================================================== |(7) 55-0710073 | | |TEAYS RIVER CONSTRUCTION COM| | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 1.000 LS | 107615.50000 107615.50| | CLEARING AND GRUBBING | | | 0010 204-01 LUMP| 20000.00000 20000.00| | MOBILIZATION | | | 0015 207-01 81.000 M3 | 24.00000 1944.00| | UNCLASSIFIED EXCAVATION | | | 0020 207-02 4.000 M3 | 80.00000 320.00| | SUBGRADE | | | 0025 211-01 4226.000 M3 | 30.00000 126780.00| | UNCLASSIFIED BORROW EXCAVATION | | | 0030 211-02 40.000 M3 | 30.00000 1200.00| | ROCK BORROW EXCAVATION | | | 0035 307-01 184.000 M3 | 90.00000 16560.00| | CLASS I AGGREGATE BASE COURSE | | | 0040 308-01 18.000 MGR | 70.00000 1260.00| | CLASS 1 AGGREGATE BASE COURSE | | | 0045 408-02 72.000 L | 0.20000 14.40| | BITUMINOUS MATERIAL | | | 0050 409-02 1592.000 L | 0.20000 318.40| | BITUMINOUS MATERIAL PRIME | | | 0055 502-01300 130.000 M2 | 180.00000 23400.00| | PORTLAND CEMENT CONCRETE APPRACH SLAB | | | 300MM | | | 0060 607-011 161.700 M | 56.00000 9055.20| | TYPE 1 GUARDRAIL, CLASS I | | | 0065 607-012 120.000 M | 40.00000 4800.00| | TYPE 1 GUARDRAIL CLASS II | | | 0070 607-101 286.000 M | 5.00000 1430.00| | TYPE 1 GUARDRAIL REMOVED AND STORED | | | 0075 607-28 2.000 EA | 750.00000 1500.00| | MODIFIED ECCENTRIC LOADER TERMINAL | | | 0080 636-07 400.000 M | 3.00000 1200.00| | ERADICATION PAVEMENT MARKINGS | | | 0085 636-08 880.000 M | 3.00000 2640.00| | TEMP PVMT MARKING-PAINT | | | 0090 636-09 808.000 M | 2.00000 1616.00| | TEMP PVMT MARKING-TAPE | | | 0095 636-11 9030.000 UN | 0.01000 90.30| | TRAFFIC CONTROL DEVICE | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 003 -9 TABULATION OF BIDS CALL ORDER : 003 CONTRACT ID : 9416002 COUNTIES : PUTNAM LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 01 SET-ASIDE : ==================================================================================================================================== |(7) 55-0710073 | | |TEAYS RIVER CONSTRUCTION COM| | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0100 636-12 5.000 EA | 200.00000 1000.00| | CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0105 636-13 50.000 EA | 2.00000 100.00| | CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0110 636-14 1000.000 HR | 0.01000 10.00| | FLAGGER | | | 0115 636-25A 1200.000 DA | 0.50000 600.00| | WARNING LIGHTS TYPE A | | | 0120 636-25B 2500.000 DA | 1.00000 2500.00| | WARNING LIGHTS TYPE B | | | 0125 639-01 LUMP| 2000.00000 2000.00| | CONSTRUCTION LAYOUT STAKES | | | 0130 640-02 LUMP| 5000.00000 5000.00| | SMALL FIELD OFFICE/STORAGE BUILDING | | | 0135 640-03 LUMP| 500.00000 500.00| | BUILDING EQUIPMENT | | | 0140 642-14 LUMP| 1500.00000 1500.00| | TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 0145 401-1(1)SG AA1 170.000 MGR | 60.00000 10200.00| | HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0150 401-1(1)S AA2 155.000 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0155 401-2(1)S AB2 16.000 MGR | | | HOT-MIX ASPHALT WEARING COURSE, SLAG | | | 0160 401-2(1)SG AB1 18.000 MGR | 110.00000 1980.00| | HOT-MIX ASPHALT WEARING COURSE, STONE | | | OR GRAVEL | | | 0165 401-3SG AC1 19.000 MGR | 110.00000 2090.00| | HOT-MIX ASPHALT PATCH AND LEVEL COURSE, | | | STONE OR GRAVEL | | | 0170 401-3S AC2 17.000 MGR | | | HOT-MIX ASPHALT PATCH AND LEVEL COURSE, | | | SLAG | | | 0175 402-01SG AD1 87.000 MGR | 110.00000 9570.00| | HMA SKID PAVEMENT, STONE/GRAVEL | | | 0180 402-01S AD2 78.000 MGR | | | HMA SKID PAVEMENT, SLAG | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 003 -10 TABULATION OF BIDS CALL ORDER : 003 CONTRACT ID : 9416002 COUNTIES : PUTNAM LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 01 SET-ASIDE : ==================================================================================================================================== |(7) 55-0710073 | | |TEAYS RIVER CONSTRUCTION COM| | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0185 636-02SG AE1 16.000 MGR | 20.00000 320.00| | AGGREGATE FOR MAINTAINING TRAFFIC, | | | STONE OR GRAVEL | | | 0190 636-02S AE2 15.000 MGR | | | AGGREGATE FOR MAINTAINING TRAFFIC, SLAG | | | SECTION TOTALS | $ 359,113.80| | ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 BRIDGE #1813 | | | 0195 203-01 LUMP| 110000.00000 110000.00| | DISMANTLING STRUCTURES | | | 0200 212-01 15.000 M3 | 30.00000 450.00| | STRUCTURE EXCAVATION | | | 0205 212-05 15.000 M3 | 70.00000 1050.00| | SELECT MATERIAL FOR BACKFILLING | | | 0210 601-02 54.000 M3 | 890.00000 48060.00| | CLASS B CONCRETE | | | 0215 601-03 181.000 M3 | 1100.00000 199100.00| | CLASS K CONCRETE | | | 0220 602-01 2484.000 KG | 2.50000 6210.00| | REIN STEEL BARS | | | 0225 602-02 30232.000 KG | 1.60000 48371.20| | EPOXY COATED REINFORCING BARS | | | 0230 606-250150 26.000 M | 14.00000 364.00| | UNDERDRAIN PIPE 150MM | | | 0235 615-01 1.000 LS | 166280.00000 166280.00| | STEEL SUPERSTRUCTURE | | | 0240 636-05 LUMP| 200000.00000 200000.00| | TEMPORARY STRUCTURES FOR MAINTAINING | | | TRAFFIC | | | 0245 639-01 LUMP| 1.00000 1.00| | CONSTRUCTION LAYOUT STAKES | | | SECTION TOTALS | $ 779,886.20| | ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 1,139,000.00| | ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 004 -1 VENDOR RANKING CALL ORDER : 004 CONTRACT ID : 9717804 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 CONTRACT DESCRIPTION : US 250 AT MARY LOU RETTON DRIVE PROJECT(S) : U325-0250/00-006.20 00 STPG 0250 103 EQ0 LOCATION: FAIRMONT 0 -------------------------------------------------------------------------------------------------------------------------- TOTAL % OVER RANK VENDOR NO./NAME BID LOW BID -------------------------------------------------------------------------------------------------------------------------- 1 55-0343932 BAYLISS & RAMEY, INC. $ 53,329.25 100.0000% 2 54-0458233 DAVIS H. ELLIOT COMPANY, INC. $ 60,000.00 112.5086% 3 55-0646159 WEST VIRGINIA SIGNAL AND LIGHT, INC. $ 68,295.00 128.0629% 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 004 -2 TABULATION OF BIDS CALL ORDER : 004 CONTRACT ID : 9717804 COUNTIES : MARION LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 04 SET-ASIDE : ==================================================================================================================================== |(1) 55-0343932 |(2) 54-0458233 |(3) 55-0646159 |BAYLISS & RAMEY, INC. |DAVIS H. ELLIOT COMPANY, INC|WEST VIRGINIA SIGNAL & LIGHT LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 TRAFFIC SIGNAL | | | 0005 204-01 LUMP| 3250.00000 3250.00| 2825.00000 2825.00| 3000.00000 3000.00 MOBILIZATION | | | 0010 636-11 4400.000 UN | 0.01000 44.00| 0.10000 440.00| 0.01000 44.00 TRAFFIC CONTROL DEVICE | | | 0015 636-14 100.000 HR | 0.10000 10.00| 1.00000 100.00| 0.01000 1.00 FLAGGER | | | 0020 660-01 LUMP| 9175.00000 9175.00| 12000.00000 12000.00| 9250.00000 9250.00 SIGNAL CONTROLLERS 01 | | | 0025 660-02LPSC 6.000 EA | 145.00000 870.00| 130.00000 780.00| 150.00000 900.00 TRAFFIC DETECTORS | | | 0030 660-03V203 9.000 EA | 142.25000 1280.25| 100.00000 900.00| 150.00000 1350.00 SIGNAL SECTIONS | | | 0035 660-03V305 20.000 EA | 142.25000 2845.00| 120.00000 2400.00| 175.00000 3500.00 SIGNAL SECTIONS | | | 0040 660-04C1 3.000 EA | 6425.00000 19275.00| 4300.00000 12900.00| 7750.00000 23250.00 SIGNAL SUPPORTS | | | 0045 660-05H 3.000 EA | 1250.00000 3750.00| 1000.00000 3000.00| 1000.00000 3000.00 JUNCTION BOXES TYPE H | | | 0050 660-07 LUMP| 9450.00000 9450.00| 18815.00000 18815.00| 19500.00000 19500.00 MISCELLANEOUS SIGNAL 01 | | | 0055 660-10D1 1.000 EA | 2500.00000 2500.00| 5000.00000 5000.00| 3500.00000 3500.00 PRIORITY CONTROL SYSTEM DETECTOR | | | 0060 663-055 20.000 M | 44.00000 880.00| 42.00000 840.00| 50.00000 1000.00 TYPE V STOP LINES | | | SECTION TOTALS | $ 53,329.25| $ 60,000.00| $ 68,295.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 53,329.25| $ 60,000.00| $ 68,295.00 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 005 -1 VENDOR RANKING CALL ORDER : 005 CONTRACT ID : 9709914 COUNTIES : MARSHALL LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 06 CONTRACT DESCRIPTION : BAYER PLANT & BENWOOD PLAZA PROJECT(S) : S326-0002/00-000.49 00 0NHG 0002 284 E00 LOCATION: BENWOOD PLAZA 0 -------------------------------------------------------------------------------------------------------------------------- TOTAL % OVER RANK VENDOR NO./NAME BID LOW BID -------------------------------------------------------------------------------------------------------------------------- 1 55-0646159 WEST VIRGINIA SIGNAL AND LIGHT, INC. $ 107,241.00 100.0000% 2 55-0343932 BAYLISS & RAMEY, INC. $ 116,772.00 108.8874% 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 005 -2 TABULATION OF BIDS CALL ORDER : 005 CONTRACT ID : 9709914 COUNTIES : MARSHALL LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 06 SET-ASIDE : ==================================================================================================================================== |(1) 55-0646159 |(2) 55-0343932 | |WEST VIRGINIA SIGNAL & LIGHT|BAYLISS & RAMEY, INC. | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 TRAFFIC SIGNAL | | | 0005 204-01 LUMP| 6000.00000 6000.00| 4500.00000 4500.00| MOBILIZATION | | | 0010 636-11 8700.000 UN | 0.01000 87.00| 0.01000 87.00| TRAFFIC CONTROL DEVICE | | | 0015 636-14 400.000 HR | 0.01000 4.00| 0.10000 40.00| FLAGGER | | | 0020 660-01 LUMP| 9500.00000 9500.00| 8500.00000 8500.00| SIGNAL CONTROLLERS 01 | | | 0025 660-01 LUMP| 9500.00000 9500.00| 8500.00000 8500.00| SIGNAL CONTROLLERS 02 | | | 0030 660-01 LUMP| 9500.00000 9500.00| 8500.00000 8500.00| SIGNAL CONTROLLERS 03 | | | 0035 660-02LPSC 18.000 EA | 125.00000 2250.00| 137.50000 2475.00| TRAFFIC DETECTORS | | | 0040 660-03V305 62.000 EA | 200.00000 12400.00| 300.00000 18600.00| SIGNAL SECTIONS | | | 0045 660-05H 18.000 EA | 750.00000 13500.00| 1275.00000 22950.00| JUNCTION BOXES TYPE H | | | 0050 660-07 LUMP| 20000.00000 20000.00| 20192.00000 20192.00| MISCELLANEOUS SIGNAL 01 | | | 0055 660-07 LUMP| 19500.00000 19500.00| 18123.00000 18123.00| MISCELLANEOUS SIGNAL 02 | | | 0060 660-07 LUMP| 5000.00000 5000.00| 4305.00000 4305.00| MISCELLANEOUS SIGNAL 03 | | | SECTION TOTALS | $ 107,241.00| $ 116,772.00| ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 107,241.00| $ 116,772.00| ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 006 -1 VENDOR RANKING CALL ORDER : 006 CONTRACT ID : 9705802R2 COUNTIES : WOOD LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 03 CONTRACT DESCRIPTION : PARKERSBURG - WILLAMSTOWN ROAD PROJECT(S) : S354-0077/00-177.44 00 00NH 0773 292 E00 LOCATION: 0.98 M N US 50 SB 0 -------------------------------------------------------------------------------------------------------------------------- TOTAL % OVER RANK VENDOR NO./NAME BID LOW BID -------------------------------------------------------------------------------------------------------------------------- 1 31-0728277 MAIDEN & JENKINS CONSTRUCTION COMPANY, INC. $ 302,500.00 100.0000% 2 55-0487806 ORDERS CONSTRUCTION COMPANY, INC. $ 929,429.40 307.2493% 3 31-4444098 ALAN STONE CO., INC. $ 988,015.00 326.6165% 4 55-0544171 FAYETTE CONSTRUCTION COMPANY, INC. $ 1,143,643.00 378.0638% 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 006 -2 TABULATION OF BIDS CALL ORDER : 006 CONTRACT ID : 9705802R2 COUNTIES : WOOD LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 03 SET-ASIDE : Standard ==================================================================================================================================== |(1) 31-0728277 |(2) 55-0487806 |(3) 31-4444098 |MAIDEN & JENKINS CONSTRUCTIO|ORDERS CONSTRUCTION COMPANY,|ALAN STONE CO., INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 SLIP CORRECTION | | | 0005 201-01 1.000 LS | 1500.00000 1500.00| 118000.00000 118000.00| 30000.00000 30000.00 CLEARING AND GRUBBING | | | 0010 204-01 LUMP| 12545.95000 12545.95| 25000.00000 25000.00| 30000.00000 30000.00 MOBILIZATION | | | 0015 207-01 14384.000 CY | 2.25000 32364.00| 7.60000 109318.40| 7.00000 100688.00 UNCLASSIFIED EXCAVATION | | | 0020 211-01 22094.000 CY | 3.70000 81747.80| 7.85000 173437.90| 10.55000 233091.70 UNCLASSIFIED BORROW EXCAVATION | | | 0025 211-02 19587.000 CY | 6.75000 132212.25| 23.00000 450501.00| 28.00000 548436.00 ROCK BORROW EXCAVATION | | | 0030 240-01(18) 75.000 LF | 35.00000 2625.00| 19.00000 1425.00| 20.00000 1500.00 CLEANING CULVERTS | | | 0035 240-02 1.000 EA | 300.00000 300.00| 400.00000 400.00| 100.00000 100.00 CLEANING INLETS | | | 0040 604-01(18)A2 24.000 LF | 36.50000 876.00| 58.00000 1392.00| 40.00000 960.00 METALLIC COATED CORRUGATED STEEL PIPE | | | 0045 604-53(18) 20.000 LF | 43.00000 860.00| 46.00000 920.00| 40.00000 800.00 RELAID CONDUIT | | | 0050 608-02(3F11I) 658.000 LF | 15.00000 9870.00| 15.40000 10133.20| 20.00000 13160.00 RIGHT-OF-WAY FENCE, FARM FIELD TYPE | | | 0055 636-11 6210.000 UN | 1.10000 6831.00| 1.17000 7265.70| 1.33000 8259.30 TRAFFIC CONTROL DEVICES | | | 0060 636-14 200.000 HR | 29.00000 5800.00| 39.00000 7800.00| 33.00000 6600.00 FLAGGER | | | 0065 636-21 20.000 DA | 20.00000 400.00| 20.00000 400.00| 33.00000 660.00 ELECTRIC ARROW | | | 0070 638-02 5.000 EA | 190.00000 950.00| 55.00000 275.00| 100.00000 500.00 RIGHT OF WAY MARKERS | | | 0075 639-01 LUMP| 5000.00000 5000.00| 14000.00000 14000.00| 6000.00000 6000.00 CONSTRUCTION LAYOUT STAKES | | | 0080 642-13 LUMP| 1500.00000 1500.00| 3500.00000 3500.00| 2000.00000 2000.00 TEMPORARY POLLUTION CONTROL | | | 0085 652-02-1 1.400 TN | 450.00000 630.00| 330.00000 462.00| 500.00000 700.00 FERTILIZER, 10-20-10 | | | 0090 652-03-2 176.000 LB | 13.00000 2288.00| 10.45000 1839.20| 10.00000 1760.00 SEED MIXTURES D | | | 0095 652-04-1 5.600 TN | 750.00000 4200.00| 600.00000 3360.00| 500.00000 2800.00 STRAW OR HAY MULCH | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 006 -3 TABULATION OF BIDS CALL ORDER : 006 CONTRACT ID : 9705802R2 COUNTIES : WOOD LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 03 SET-ASIDE : Standard ==================================================================================================================================== |(1) 31-0728277 |(2) 55-0487806 |(3) 31-4444098 |MAIDEN & JENKINS CONSTRUCTIO|ORDERS CONSTRUCTION COMPANY,|ALAN STONE CO., INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION TOTALS | $ 302,500.00| $ 929,429.40| $ 988,015.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 302,500.00| $ 929,429.40| $ 988,015.00 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 006 -4 TABULATION OF BIDS CALL ORDER : 006 CONTRACT ID : 9705802R2 COUNTIES : WOOD LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 03 SET-ASIDE : Standard ==================================================================================================================================== |(4) 55-0544171 | | |FAYETTE CONSTRUCTION COMPANY| | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 SLIP CORRECTION | | | 0005 201-01 1.000 LS | 25000.00000 25000.00| | CLEARING AND GRUBBING | | | 0010 204-01 LUMP| 15000.00000 15000.00| | MOBILIZATION | | | 0015 207-01 14384.000 CY | 6.00000 86304.00| | UNCLASSIFIED EXCAVATION | | | 0020 211-01 22094.000 CY | 12.00000 265128.00| | UNCLASSIFIED BORROW EXCAVATION | | | 0025 211-02 19587.000 CY | 35.00000 685545.00| | ROCK BORROW EXCAVATION | | | 0030 240-01(18) 75.000 LF | 20.00000 1500.00| | CLEANING CULVERTS | | | 0035 240-02 1.000 EA | 1000.00000 1000.00| | CLEANING INLETS | | | 0040 604-01(18)A2 24.000 LF | 200.00000 4800.00| | METALLIC COATED CORRUGATED STEEL PIPE | | | 0045 604-53(18) 20.000 LF | 200.00000 4000.00| | RELAID CONDUIT | | | 0050 608-02(3F11I) 658.000 LF | 20.00000 13160.00| | RIGHT-OF-WAY FENCE, FARM FIELD TYPE | | | 0055 636-11 6210.000 UN | 2.00000 12420.00| | TRAFFIC CONTROL DEVICES | | | 0060 636-14 200.000 HR | 35.00000 7000.00| | FLAGGER | | | 0065 636-21 20.000 DA | 25.00000 500.00| | ELECTRIC ARROW | | | 0070 638-02 5.000 EA | 150.00000 750.00| | RIGHT OF WAY MARKERS | | | 0075 639-01 LUMP| 12000.00000 12000.00| | CONSTRUCTION LAYOUT STAKES | | | 0080 642-13 LUMP| 2000.00000 2000.00| | TEMPORARY POLLUTION CONTROL | | | 0085 652-02-1 1.400 TN | 1600.00000 2240.00| | FERTILIZER, 10-20-10 | | | 0090 652-03-2 176.000 LB | 11.00000 1936.00| | SEED MIXTURES D | | | 0095 652-04-1 5.600 TN | 600.00000 3360.00| | STRAW OR HAY MULCH | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 006 -5 TABULATION OF BIDS CALL ORDER : 006 CONTRACT ID : 9705802R2 COUNTIES : WOOD LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 03 SET-ASIDE : Standard ==================================================================================================================================== |(4) 55-0544171 | | |FAYETTE CONSTRUCTION COMPANY| | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION TOTALS | $ 1,143,643.00| | ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 1,143,643.00| | ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 007 -1 VENDOR RANKING CALL ORDER : 007 CONTRACT ID : 9315206 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 CONTRACT DESCRIPTION : DELBARTON DBL ARCH BRIDGE PROJECT(S) : S330-0052/00-031.13 00 0STP 0052 127 000 LOCATION: OVER PIGEON CR, 0.4 MI E CO 65/12 0 -------------------------------------------------------------------------------------------------------------------------- TOTAL % OVER RANK VENDOR NO./NAME BID LOW BID -------------------------------------------------------------------------------------------------------------------------- 1 55-0417282 TURMAN CONSTRUCTION CO. $ 965,670.00 100.0000% 2 61-0911548 ROBERTS CONSTRUCTION COMPANY $ 1,033,309.54 107.0044% 3 31-1316393 AHERN & ASSOCIATES, INC. $ 1,072,000.00 111.0110% 4 62-1345425 BILCO CONSTRUCTION COMPANY, INC. $ 1,112,734.00 115.2292% 5 55-0487806 ORDERS CONSTRUCTION COMPANY, INC. $ 1,114,734.71 115.4364% 6 55-0710073 TEAYS RIVER CONSTRUCTION COMPANY $ 1,199,239.44 124.1872% 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 007 -2 TABULATION OF BIDS CALL ORDER : 007 CONTRACT ID : 9315206 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(1) 55-0417282 |(2) 61-0911548 |(3) 31-1316393 |TURMAN CONSTRUCTION CO. |ROBERTS CONSTRUCTION COMPANY|AHERN & ASSOCIATES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 1.000 LS | 25000.00000 25000.00| 14000.00000 14000.00| 20000.00000 20000.00 CLEARING AND GRUBBING | | | 0010 202-01 1.000 LS | 12500.00000 12500.00| 5000.00000 5000.00| 2000.00000 2000.00 BUILDING DEMOLITION 202-01(01) | | | 0015 204-01 LUMP| 24000.00000 24000.00| 30000.00000 30000.00| 33000.00000 33000.00 MOBILIZATION | | | 0020 207-01 1668.000 M3 | 15.00000 25020.00| 16.00000 26688.00| 15.00000 25020.00 UNCLASSIFIED EXCAVATION | | | 0025 207-02 339.000 M3 | 45.00000 15255.00| 60.00000 20340.00| 50.00000 16950.00 SUBGRADE | | | 0030 207-34 4250.000 M2 | 1.55000 6587.50| 3.00000 12750.00| 1.50000 6375.00 FABRIC FOR SEPARATION | | | 0035 211-01 1384.000 M3 | 17.50000 24220.00| 20.00000 27680.00| 15.00000 20760.00 UNCLASSIFIED BORROW EXCAVATION | | | 0040 307-01 1017.000 M3 | 50.00000 50850.00| 60.00000 61020.00| 50.00000 50850.00 CLASS I AGGREGATE BASE COURSE | | | 0045 308-01 63.000 MGR | 35.00000 2205.00| 48.00000 3024.00| 50.00000 3150.00 CLASS 1 AGGREGATE BASE COURSE | | | 0050 409-02 6023.000 L | 0.30000 1806.90| 0.34000 2047.82| 0.31000 1867.13 BITUMINOUS MATERIAL PRIME | | | 0055 502-01300 144.000 M2 | 155.00000 22320.00| 150.00000 21600.00| 140.00000 20160.00 PORTLAND CEMENT CONCRETE APPRACH SLAB | | | 300MM | | | 0060 604-010375A2 5.500 M | 150.00000 825.00| 165.00000 907.50| 85.00000 467.50 METALLIC COATED CORRUGATED STEEL PIPE, | | | 375MM, A2 | | | 0065 604-010450A2 19.500 M | 150.00000 2925.00| 185.00000 3607.50| 155.00000 3022.50 METALLIC COATED CORRUGATED STEEL PIPE, | | | 450MM, A2 | | | 0070 604-090375 1.000 EA | 250.00000 250.00| 320.00000 320.00| 165.00000 165.00 END SECTION FOR CORRUGATED STEEL PIPE | | | 375MM | | | 0075 605-04 1.000 EA | 1750.00000 1750.00| 1800.00000 1800.00| 1200.00000 1200.00 TYPE B INLET | | | 0080 605-09 1.000 EA | 1850.00000 1850.00| 2500.00000 2500.00| 1500.00000 1500.00 TYPE G INLET | | | 0085 607-011 102.500 M | 68.00000 6970.00| 76.00000 7790.00| 68.00000 6970.00 TYPE 1 GUARDRAIL, CLASS I | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 007 -3 TABULATION OF BIDS CALL ORDER : 007 CONTRACT ID : 9315206 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(1) 55-0417282 |(2) 61-0911548 |(3) 31-1316393 |TURMAN CONSTRUCTION CO. |ROBERTS CONSTRUCTION COMPANY|AHERN & ASSOCIATES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0090 607-28 4.000 EA | 800.00000 3200.00| 900.00000 3600.00| 800.00000 3200.00 MODIFIED ECCENTRIC LOADER TERMINAL | | | 0095 610-012 91.000 M | 120.00000 10920.00| 95.00000 8645.00| 85.00000 7735.00 PLAIN CONCRETE CURBING TYPE II | | | 0100 636-02SG 20.000 MGR | 30.00000 600.00| 48.00000 960.00| 25.00000 500.00 AGGREGATE FOR MAINTAINING TRAFFIC, | | | STONE OR GRAVEL | | | 0105 636-05 LUMP| 60000.00000 60000.00| 40000.00000 40000.00| 112000.00000 112000.00 TEMPORARY STRUCTURES FOR MAINTAINING | | | TRAFFIC | | | 0110 636-07 200.000 M | 3.60000 720.00| 2.80000 560.00| 2.30000 460.00 ERADICATION PAVEMENT MARKINGS | | | 0115 636-09 880.000 M | 4.20000 3696.00| 4.50000 3960.00| 4.26000 3748.80 TEMP PVMT MARKING-TAPE | | | 0120 636-11 9304.000 UN | 1.25000 11630.00| 1.30000 12095.20| 1.14000 10606.56 TRAFFIC CONTROL DEVICE | | | 0125 636-12 2.000 EA | 290.00000 580.00| 360.00000 720.00| 300.00000 600.00 CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0130 636-13 100.000 EA | 3.83000 383.00| 3.60000 360.00| 3.00000 300.00 CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0135 636-14 500.000 HR | 30.00000 15000.00| 40.00000 20000.00| 20.00000 10000.00 FLAGGER | | | 0140 636-19 101.000 M | 92.00000 9292.00| 104.00000 10504.00| 92.00000 9292.00 TEMPORARY GUARDRAIL BARRIERS | | | 0145 636-25B 1080.000 DA | 1.90000 2052.00| 1.80000 1944.00| 1.59000 1717.20 WARNING LIGHTS TYPE B | | | 0150 638-02 16.000 EA | 70.00000 1120.00| 75.00000 1200.00| 50.00000 800.00 RIGHT OF WAY MARKERS | | | 0155 639-01 LUMP| 4500.00000 4500.00| 6000.00000 6000.00| 10000.00000 10000.00 CONSTRUCTION LAYOUT STAKES | | | 0160 640-01 LUMP| 7500.00000 7500.00| 10000.00000 10000.00| 15000.00000 15000.00 STANDARD FIELD OFFICE AND STORAGE | | | BUILDING | | | 0165 640-03 LUMP| 1500.00000 1500.00| 3000.00000 3000.00| 3000.00000 3000.00 BUILDING EQUIPMENT | | | 0170 642-14 LUMP| 1500.00000 1500.00| 4500.00000 4500.00| 2500.00000 2500.00 TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 007 -4 TABULATION OF BIDS CALL ORDER : 007 CONTRACT ID : 9315206 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(1) 55-0417282 |(2) 61-0911548 |(3) 31-1316393 |TURMAN CONSTRUCTION CO. |ROBERTS CONSTRUCTION COMPANY|AHERN & ASSOCIATES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0175 681-01 LUMP| 2568.00000 2568.00| 8000.00000 8000.00| 2250.00000 2250.00 ASBESTOS ABATEMENT 681-01(01) | | | 0180 401-1(1)SG AA1 1244.000 MGR | 60.10000 74764.40| 67.00000 83348.00| 60.00000 74640.00 HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0185 401-1(1)S AA2 1123.000 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0190 402-01SG BB1 144.000 MGR | | | HMA SKID PAVEMENT, STONE/GRAVEL | | | 0195 402-01S BB2 130.000 MGR | 67.10000 8723.00| 75.00000 9750.00| 67.00000 8710.00 HMA SKID PAVEMENT, SLAG | | | SECTION TOTALS | $ 444,582.80| $ 470,221.02| $ 490,516.69 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 BRIDGE | | | 0200 203-01 LUMP| 25000.00000 25000.00| 31000.00000 31000.00| 87851.31000 87851.31 DISMANTLING STRUCTURES | | | 0205 211-02 455.000 M3 | 50.00000 22750.00| 75.00000 34125.00| 40.00000 18200.00 ROCK BORROW EXCAVATION | | | 0210 212-01 78.000 M3 | 50.00000 3900.00| 26.00000 2028.00| 10.00000 780.00 STRUCTURE EXCAVATION | | | 0215 212-05 30.000 M3 | 75.00000 2250.00| 80.00000 2400.00| 200.00000 6000.00 SELECT MATERIAL FOR BACKFILLING | | | 0220 601-02 116.000 M3 | 475.00000 55100.00| 525.00000 60900.00| 525.00000 60900.00 CLASS B CONCRETE | | | 0225 601-03 130.000 M3 | 675.00000 87750.00| 750.00000 97500.00| 870.00000 113100.00 CLASS K CONCRETE | | | 0230 602-02 24168.000 KG | 1.65000 39877.20| 1.64000 39635.52| 1.50000 36252.00 EPOXY COATED REINFORCING BARS | | | 0235 615-01 79128.000 LS | 255000.00000 255000.00| 252800.00000 252800.00| 225000.00000 225000.00 STEEL SUPERSTRUCTURE | | | 0240 616-05H250062 132.000 M | 155.00000 20460.00| 225.00000 29700.00| 200.00000 26400.00 STEEL BEARING PILES, HP 250X62, | | | PRE-DRILLED AND DRIVEN | | | 0245 639-01 LUMP| 4500.00000 4500.00| 8000.00000 8000.00| 5000.00000 5000.00 CONSTRUCTION LAYOUT STAKES | | | 0250 640-04 LUMP| 4500.00000 4500.00| 5000.00000 5000.00| 2000.00000 2000.00 COMPUTER SYSTEM FOR FIELD OFFICE | | | SECTION TOTALS | $ 521,087.20| $ 563,088.52| $ 581,483.31 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 965,670.00| $ 1,033,309.54| $ 1,072,000.00 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 007 -5 TABULATION OF BIDS CALL ORDER : 007 CONTRACT ID : 9315206 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(4) 62-1345425 |(5) 55-0487806 |(6) 55-0710073 |BILCO CONSTRUCTION COMPANY, |ORDERS CONSTRUCTION COMPANY,|TEAYS RIVER CONSTRUCTION COM LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 1.000 LS | 5500.00000 5500.00| 8000.00000 8000.00| 50000.00000 50000.00 CLEARING AND GRUBBING | | | 0010 202-01 1.000 LS | 1250.00000 1250.00| 7900.00000 7900.00| 7500.00000 7500.00 BUILDING DEMOLITION 202-01(01) | | | 0015 204-01 LUMP| 28000.00000 28000.00| 28600.00000 28600.00| 15000.00000 15000.00 MOBILIZATION | | | 0020 207-01 1668.000 M3 | 9.50000 15846.00| 23.00000 38364.00| 22.00000 36696.00 UNCLASSIFIED EXCAVATION | | | 0025 207-02 339.000 M3 | 49.00000 16611.00| 75.00000 25425.00| 58.00000 19662.00 SUBGRADE | | | 0030 207-34 4250.000 M2 | 1.50000 6375.00| 1.25000 5312.50| 0.50000 2125.00 FABRIC FOR SEPARATION | | | 0035 211-01 1384.000 M3 | 13.00000 17992.00| 19.50000 26988.00| 24.00000 33216.00 UNCLASSIFIED BORROW EXCAVATION | | | 0040 307-01 1017.000 M3 | 49.00000 49833.00| 75.00000 76275.00| 50.00000 50850.00 CLASS I AGGREGATE BASE COURSE | | | 0045 308-01 63.000 MGR | 25.00000 1575.00| 44.50000 2803.50| 60.00000 3780.00 CLASS 1 AGGREGATE BASE COURSE | | | 0050 409-02 6023.000 L | 0.50000 3011.50| 0.34000 2047.82| 0.30000 1806.90 BITUMINOUS MATERIAL PRIME | | | 0055 502-01300 144.000 M2 | 150.00000 21600.00| 178.00000 25632.00| 165.00000 23760.00 PORTLAND CEMENT CONCRETE APPRACH SLAB | | | 300MM | | | 0060 604-010375A2 5.500 M | 130.00000 715.00| 183.00000 1006.50| 300.00000 1650.00 METALLIC COATED CORRUGATED STEEL PIPE, | | | 375MM, A2 | | | 0065 604-010450A2 19.500 M | 164.00000 3198.00| 187.00000 3646.50| 135.00000 2632.50 METALLIC COATED CORRUGATED STEEL PIPE, | | | 450MM, A2 | | | 0070 604-090375 1.000 EA | 300.00000 300.00| 110.00000 110.00| 200.00000 200.00 END SECTION FOR CORRUGATED STEEL PIPE | | | 375MM | | | 0075 605-04 1.000 EA | 2200.00000 2200.00| 2100.00000 2100.00| 800.00000 800.00 TYPE B INLET | | | 0080 605-09 1.000 EA | 2200.00000 2200.00| 2000.00000 2000.00| 1000.00000 1000.00 TYPE G INLET | | | 0085 607-011 102.500 M | 88.00000 9020.00| 76.00000 7790.00| 70.00000 7175.00 TYPE 1 GUARDRAIL, CLASS I | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 007 -6 TABULATION OF BIDS CALL ORDER : 007 CONTRACT ID : 9315206 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(4) 62-1345425 |(5) 55-0487806 |(6) 55-0710073 |BILCO CONSTRUCTION COMPANY, |ORDERS CONSTRUCTION COMPANY,|TEAYS RIVER CONSTRUCTION COM LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0090 607-28 4.000 EA | 935.00000 3740.00| 900.00000 3600.00| 1000.00000 4000.00 MODIFIED ECCENTRIC LOADER TERMINAL | | | 0095 610-012 91.000 M | 90.00000 8190.00| 132.00000 12012.00| 100.00000 9100.00 PLAIN CONCRETE CURBING TYPE II | | | 0100 636-02SG 20.000 MGR | 25.00000 500.00| 28.00000 560.00| 50.00000 1000.00 AGGREGATE FOR MAINTAINING TRAFFIC, | | | STONE OR GRAVEL | | | 0105 636-05 LUMP| 191000.00000 191000.00| 90000.00000 90000.00| 175000.00000 175000.00 TEMPORARY STRUCTURES FOR MAINTAINING | | | TRAFFIC | | | 0110 636-07 200.000 M | 3.50000 700.00| 4.00000 800.00| 3.25000 650.00 ERADICATION PAVEMENT MARKINGS | | | 0115 636-09 880.000 M | 4.50000 3960.00| 4.70000 4136.00| 4.00000 3520.00 TEMP PVMT MARKING-TAPE | | | 0120 636-11 9304.000 UN | 1.00000 9304.00| 1.40000 13025.60| 0.01000 93.04 TRAFFIC CONTROL DEVICE | | | 0125 636-12 2.000 EA | 0.50000 1.00| 325.00000 650.00| 200.00000 400.00 CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0130 636-13 100.000 EA | 0.01000 1.00| 4.30000 430.00| 3.00000 300.00 CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0135 636-14 500.000 HR | 33.00000 16500.00| 38.00000 19000.00| 0.01000 5.00 FLAGGER | | | 0140 636-19 101.000 M | 85.00000 8585.00| 0.01000 1.01| 92.00000 9292.00 TEMPORARY GUARDRAIL BARRIERS | | | 0145 636-25B 1080.000 DA | 2.50000 2700.00| 2.15000 2322.00| 2.00000 2160.00 WARNING LIGHTS TYPE B | | | 0150 638-02 16.000 EA | 125.00000 2000.00| 55.00000 880.00| 25.00000 400.00 RIGHT OF WAY MARKERS | | | 0155 639-01 LUMP| 3000.50000 3000.50| 13000.00000 13000.00| 3000.00000 3000.00 CONSTRUCTION LAYOUT STAKES | | | 0160 640-01 LUMP| 9000.00000 9000.00| 9300.00000 9300.00| 8000.00000 8000.00 STANDARD FIELD OFFICE AND STORAGE | | | BUILDING | | | 0165 640-03 LUMP| 2000.00000 2000.00| 1000.00000 1000.00| 500.00000 500.00 BUILDING EQUIPMENT | | | 0170 642-14 LUMP| 1500.00000 1500.00| 2900.00000 2900.00| 500.00000 500.00 TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 007 -7 TABULATION OF BIDS CALL ORDER : 007 CONTRACT ID : 9315206 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(4) 62-1345425 |(5) 55-0487806 |(6) 55-0710073 |BILCO CONSTRUCTION COMPANY, |ORDERS CONSTRUCTION COMPANY,|TEAYS RIVER CONSTRUCTION COM LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0175 681-01 LUMP| 6000.00000 6000.00| 2250.00000 2250.00| 5000.00000 5000.00 ASBESTOS ABATEMENT 681-01(01) | | | 0180 401-1(1)SG AA1 1244.000 MGR | 65.00000 80860.00| 68.00000 84592.00| 70.00000 87080.00 HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0185 401-1(1)S AA2 1123.000 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0190 402-01SG BB1 144.000 MGR | | | 80.00000 11520.00 HMA SKID PAVEMENT, STONE/GRAVEL | | | 0195 402-01S BB2 130.000 MGR | 74.00000 9620.00| 75.00000 9750.00| HMA SKID PAVEMENT, SLAG | | | SECTION TOTALS | $ 544,388.00| $ 534,209.43| $ 579,373.44 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 BRIDGE | | | 0200 203-01 LUMP| 73500.00000 73500.00| 38000.00000 38000.00| 77000.00000 77000.00 DISMANTLING STRUCTURES | | | 0205 211-02 455.000 M3 | 50.00000 22750.00| 50.00000 22750.00| 40.00000 18200.00 ROCK BORROW EXCAVATION | | | 0210 212-01 78.000 M3 | 44.00000 3432.00| 100.00000 7800.00| 25.00000 1950.00 STRUCTURE EXCAVATION | | | 0215 212-05 30.000 M3 | 100.00000 3000.00| 135.00000 4050.00| 150.00000 4500.00 SELECT MATERIAL FOR BACKFILLING | | | 0220 601-02 116.000 M3 | 535.00000 62060.00| 663.00000 76908.00| 450.00000 52200.00 CLASS B CONCRETE | | | 0225 601-03 130.000 M3 | 635.00000 82550.00| 843.00000 109590.00| 775.00000 100750.00 CLASS K CONCRETE | | | 0230 602-02 24168.000 KG | 1.75000 42294.00| 1.71000 41327.28| 2.00000 48336.00 EPOXY COATED REINFORCING BARS | | | 0235 615-01 79128.000 LS | 245000.00000 245000.00| 223000.00000 223000.00| 285529.00000 285529.00 STEEL SUPERSTRUCTURE | | | 0240 616-05H250062 132.000 M | 180.00000 23760.00| 350.00000 46200.00| 200.00000 26400.00 STEEL BEARING PILES, HP 250X62, | | | PRE-DRILLED AND DRIVEN | | | 0245 639-01 LUMP| 2500.00000 2500.00| 6500.00000 6500.00| 1.00000 1.00 CONSTRUCTION LAYOUT STAKES | | | 0250 640-04 LUMP| 7500.00000 7500.00| 4400.00000 4400.00| 5000.00000 5000.00 COMPUTER SYSTEM FOR FIELD OFFICE | | | SECTION TOTALS | $ 568,346.00| $ 580,525.28| $ 619,866.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 1,112,734.00| $ 1,114,734.71| $ 1,199,239.44 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 008 -1 VENDOR RANKING CALL ORDER : 008 CONTRACT ID : 9606809 COUNTIES : BERKELEY LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 05 CONTRACT DESCRIPTION : MOLER AVENUE INTERSECTION PROJECT(S) : U302-0045/00-018.34 00 0STP 0045 027 EQ0 LOCATION: CR 45/6 @ WV45 - CR 45/6 I/S 45/5 0 -------------------------------------------------------------------------------------------------------------------------- TOTAL % OVER RANK VENDOR NO./NAME BID LOW BID -------------------------------------------------------------------------------------------------------------------------- 1 23-1374051 UNION EQUIPMENT CO., DIVISION NEW ENTERPRISE STONE & LIME CO $ 262,827.30 100.0000% 2 55-0492296 JEFFERSON ASPHALT PRODUCTS COMPANY, INC. & SUBSIDIARY $ 282,864.39 107.6236% 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 008 -2 TABULATION OF BIDS CALL ORDER : 008 CONTRACT ID : 9606809 COUNTIES : BERKELEY LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 05 SET-ASIDE : Standard ==================================================================================================================================== |(1) 23-1374051 |(2) 55-0492296 | |UNION EQUIPMENT CO. |JEFFERSON ASPHALT PRODUCTS C| LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 GRADE,DRAIN, PAVE AND TRAFFIC SIGNAL | | | 0005 204-01 LUMP| 7700.00000 7700.00| 17500.00000 17500.00| MOBILIZATION | | | 0010 207-01 870.000 M3 | 36.00000 31320.00| 21.00000 18270.00| UNCLASSIFIED EXCAVATION | | | 0015 207-02 203.000 M3 | 57.00000 11571.00| 38.85000 7886.55| SUBGRADE | | | 0020 307-01 263.000 M3 | 50.00000 13150.00| 38.85000 10217.55| CLASS I AGGREGATE BASE COURSE | | | 0025 408-02 658.000 L | 0.40000 263.20| 0.53000 348.74| BITUMINOUS MATERIAL | | | 0030 409-02 1436.000 L | 0.40000 574.40| 0.53000 761.08| BITUMINOUS MATERIAL PRIME | | | 0035 601-06 7.500 M3 | 200.00000 1500.00| 425.00000 3187.50| CLASS D CONCRETE | | | 0040 604-010450A2 89.560 M | 75.00000 6717.00| 211.00000 18897.16| METALLIC COATED CORRUGATED STEEL PIPE, | | | 450MM, A2 | | | 0045 604-3706003 6.150 M | 120.00000 738.00| 211.00000 1297.65| REINFORCED CONCRETE PIPE, 600MM, CLASS | | | III | | | 0050 604-546003 23.000 M | 1000.00000 23000.00| 1040.00000 23920.00| JACKED CONDUIT, REINFORCED CONCRETE | | | PIPE, 600MM, CLASS III | | | 0055 605-09 5.000 EA | 1800.00000 9000.00| 2200.00000 11000.00| TYPE G INLET | | | 0060 606-200150 88.300 M | 56.00000 4944.80| 26.20000 2313.46| AGGREGATE FILL FABRIC UNDERDRAIN 150MM | | | 0065 636-07 1360.000 M | 1.50000 2040.00| 5.50000 7480.00| ERADICATION PAVEMENT MARKINGS | | | 0070 636-11 10510.000 UN | 1.40000 14714.00| 2.50000 26275.00| TRAFFIC CONTROL DEVICE | | | 0075 636-13 20.000 EA | 6.00000 120.00| 5.00000 100.00| CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0080 636-14 350.000 HR | 37.00000 12950.00| 32.00000 11200.00| FLAGGER | | | 0085 636-24 22.500 M | 50.00000 1125.00| 148.00000 3330.00| TEMPORARY PIPE FOR MAINTAINING TRAFFIC | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 008 -3 TABULATION OF BIDS CALL ORDER : 008 CONTRACT ID : 9606809 COUNTIES : BERKELEY LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 05 SET-ASIDE : Standard ==================================================================================================================================== |(1) 23-1374051 |(2) 55-0492296 | |UNION EQUIPMENT CO. |JEFFERSON ASPHALT PRODUCTS C| LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0090 636-25A 60.000 DA | 1.00000 60.00| 4.40000 264.00| WARNING LIGHTS TYPE A | | | 0095 636-25B 260.000 DA | 3.00000 780.00| 2.75000 715.00| WARNING LIGHTS TYPE B | | | 0100 638-02 14.000 EA | 50.00000 700.00| 100.00000 1400.00| RIGHT OF WAY MARKERS | | | 0105 639-01 LUMP| 5000.00000 5000.00| 10000.00000 10000.00| CONSTRUCTION LAYOUT STAKES | | | 0110 642-11 40.000 EA | 5.00000 200.00| 5.00000 200.00| HAY OR STRAW BALES | | | 0115 660-01 LUMP| 9500.00000 9500.00| 9945.00000 9945.00| SIGNAL CONTROLLERS | | | 0120 660-02LPSC 6.000 EA | 250.00000 1500.00| 250.00000 1500.00| TRAFFIC DETECTORS | | | 0125 660-03V305 18.000 EA | 160.00000 2880.00| 165.00000 2970.00| SIGNAL SECTIONS | | | 0130 660-04C1 3.000 EA | 5800.00000 17400.00| 6110.00000 18330.00| SIGNAL SUPPORTS | | | 0135 660-05H 3.000 EA | 850.00000 2550.00| 890.00000 2670.00| JUNCTION BOXES TYPE H | | | 0140 660-07 LUMP| 13200.00000 13200.00| 13890.00000 13890.00| MISCELLANEOUS SIGNAL | | | 0145 663-055 26.000 M | 42.00000 1092.00| 44.45000 1155.70| TYPE V STOP LINES | | | 0150 307-01S AA1 2030.000 MGR | | | CLASS 1 AGGREGATE BASE COURSE SLAG | | | 0155 307-01SG AA2 2137.000 MGR | 15.70000 33550.90| 13.25000 28315.25| CLASS 1 AGGREGATE BASE COURSE | | | STONE/GRAVE | | | 0160 308-01S BB1 97.000 MGR | | | CLASS I AGGREGATE BASE COURSE, SLAG | | | 0165 308-01SG BB2 102.000 MGR | 40.00000 4080.00| 22.00000 2244.00| CLASS I AGGREGATE BASE COURSE, | | | STONE/GRAVEL | | | 0170 401-1(1)S CC1 233.000 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0175 401-1(1)SG CC2 245.000 MGR | 46.00000 11270.00| 45.75000 11208.75| HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0180 401-1(2)S DD1 88.000 MGR | | | HOT-MIX ASPHALT BASE COURSE, SLAG | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 008 -4 TABULATION OF BIDS CALL ORDER : 008 CONTRACT ID : 9606809 COUNTIES : BERKELEY LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 05 SET-ASIDE : Standard ==================================================================================================================================== |(1) 23-1374051 |(2) 55-0492296 | |UNION EQUIPMENT CO. |JEFFERSON ASPHALT PRODUCTS C| LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0185 401-1(2)SG DD2 93.000 MGR | 48.00000 4464.00| 49.00000 4557.00| HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0190 401-7S EE1 21.000 MGR | | | SCRATCH COURSE, SLAG | | | 0195 401-7SG EE2 22.000 MGR | 84.00000 1848.00| 55.00000 1210.00| SRCATCH COURSE, STONE OR GRAVEL | | | 0200 402-01S FF1 143.000 MGR | | | HMA SKID PAVEMENT, SLAG | | | 0205 402-01SG FF2 151.000 MGR | 75.00000 11325.00| 55.00000 8305.00| HMA SKID PAVEMENT, STONE/GRAVEL | | | SECTION TOTALS | $ 262,827.30| $ 282,864.39| ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 262,827.30| $ 282,864.39| ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 009 -1 VENDOR RANKING CALL ORDER : 009 CONTRACT ID : 9724102 COUNTIES : HAMPSHIRE LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 05 CONTRACT DESCRIPTION : GRACE BRIDGE #1265.1 PROJECT(S) : S314-0028/00-022.28 00 LOCATION: WV 28 OVER SOUTH BRANCH POTOMAC LOCATED 0.03 MILE S CR 28/5 0 -------------------------------------------------------------------------------------------------------------------------- TOTAL % OVER RANK VENDOR NO./NAME BID LOW BID -------------------------------------------------------------------------------------------------------------------------- 1 59-1660700 DAMALOS & SONS INCORPORATED $ 382,210.50 100.0000% 2 59-2564575 MPG CONSTRUCTION, INC. $ 428,600.00 112.1371% 3 59-3105837 V. H. P. ENTERPRISES, INC. $ 468,000.00 122.4456% 4 34-1564476 NORTH STAR PAINTING COMPANY, INC. $ 541,211.50 141.6003% 5 55-0588442 W. R. MOLLOHAN, INC. $ 583,735.25 152.7261% 6 34-1178150 CORCON, INC. $ 742,326.75 194.2193% 7 55-0614471 SPECIALTY GROUPS, INC. $ 745,000.00 194.9187% 8 25-1196187 MANGANAS PAINTING CO., INC. $ 754,325.00 197.3585% 59-2797922 GLOBAL CONSTRUCTION, INC. IRREGULAR 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 009 -2 TABULATION OF BIDS CALL ORDER : 009 CONTRACT ID : 9724102 COUNTIES : HAMPSHIRE LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 05 SET-ASIDE : Standard ==================================================================================================================================== |(1) 59-1660700 |(2) 59-2564575 |(3) 59-3105837 |DAMALOS & SONS INCORPORATED |MPG CONSTRUCTION, INC. |V. H. P. ENTERPRISES, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 CLEAN AND PAINT GRACE BRIDGE | | | 0005 204-01 LUMP| 5000.00000 5000.00| 42000.00000 42000.00| 500.00000 500.00 MOBILIZATION | | | 0010 636-11 6505.000 UN | 0.10000 650.50| 0.75000 4878.75| 0.10000 650.50 TRAFFIC CONTROL DEVICES | | | 0015 636-14 500.000 HR | 1.00000 500.00| 12.00000 6000.00| 10.00000 5000.00 FLAGGER | | | 0020 636-23(01) 1.000 LS | 1000.00000 1000.00| 30000.00000 30000.00| 200.00000 200.00 TEMPORARY TRAFFIC SIGNAL | | | 0025 636-25(B) 600.000 DA | 0.10000 60.00| 1.00000 600.00| 0.05000 30.00 WARNING LIGHTS | | | 0030 688-02 LUMP| 370000.00000 370000.00| 211121.25000 211121.25| 459619.50000 459619.50 CLEANING AND PAINTING EXISTING STEEL | | | BRIDGES COATED WITH LEAD BASE PAINT | | | 0035 688-03 LUMP| 5000.00000 5000.00| 134000.00000 134000.00| 2000.00000 2000.00 CONTAINMENT AND DISPOSAL OF SPENT | | | MATERIAL | | | SECTION TOTALS | $ 382,210.50| $ 428,600.00| $ 468,000.00 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 382,210.50| $ 428,600.00| $ 468,000.00 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 009 -3 TABULATION OF BIDS CALL ORDER : 009 CONTRACT ID : 9724102 COUNTIES : HAMPSHIRE LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 05 SET-ASIDE : Standard ==================================================================================================================================== |(4) 34-1564476 |(5) 55-0588442 |(6) 34-1178150 |NORTH STAR PAINTING COMPANY,|W. R. MOLLOHAN, INC. |CORCON, INC. LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 CLEAN AND PAINT GRACE BRIDGE | | | 0005 204-01 LUMP| 10000.00000 10000.00| 25000.00000 25000.00| 27000.00000 27000.00 MOBILIZATION | | | 0010 636-11 6505.000 UN | 0.10000 650.50| 2.05000 13335.25| 1.35000 8781.75 TRAFFIC CONTROL DEVICES | | | 0015 636-14 500.000 HR | 1.00000 500.00| 10.00000 5000.00| 26.75000 13375.00 FLAGGER | | | 0020 636-23(01) 1.000 LS | 1.00000 1.00| 14000.00000 14000.00| 12000.00000 12000.00 TEMPORARY TRAFFIC SIGNAL | | | 0025 636-25(B) 600.000 DA | 0.10000 60.00| 2.35000 1410.00| 1.95000 1170.00 WARNING LIGHTS | | | 0030 688-02 LUMP| 400000.00000 400000.00| 395990.00000 395990.00| 500000.00000 500000.00 CLEANING AND PAINTING EXISTING STEEL | | | BRIDGES COATED WITH LEAD BASE PAINT | | | 0035 688-03 LUMP| 130000.00000 130000.00| 129000.00000 129000.00| 180000.00000 180000.00 CONTAINMENT AND DISPOSAL OF SPENT | | | MATERIAL | | | SECTION TOTALS | $ 541,211.50| $ 583,735.25| $ 742,326.75 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 541,211.50| $ 583,735.25| $ 742,326.75 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 009 -4 TABULATION OF BIDS CALL ORDER : 009 CONTRACT ID : 9724102 COUNTIES : HAMPSHIRE LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 05 SET-ASIDE : Standard ==================================================================================================================================== |(7) 55-0614471 |(8) 25-1196187 | |SPECIALTY GROUPS, INC. |MANGANAS PAINTING CO., INC. | LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 CLEAN AND PAINT GRACE BRIDGE | | | 0005 204-01 LUMP| 27000.00000 27000.00| 40000.00000 40000.00| MOBILIZATION | | | 0010 636-11 6505.000 UN | 1.20000 7806.00| 5.00000 32525.00| TRAFFIC CONTROL DEVICES | | | 0015 636-14 500.000 HR | 1.00000 500.00| 20.00000 10000.00| FLAGGER | | | 0020 636-23(01) 1.000 LS | 13000.00000 13000.00| 30000.00000 30000.00| TEMPORARY TRAFFIC SIGNAL | | | 0025 636-25(B) 600.000 DA | 2.00000 1200.00| 3.00000 1800.00| WARNING LIGHTS | | | 0030 688-02 LUMP| 347747.00000 347747.00| 400000.00000 400000.00| CLEANING AND PAINTING EXISTING STEEL | | | BRIDGES COATED WITH LEAD BASE PAINT | | | 0035 688-03 LUMP| 347747.00000 347747.00| 240000.00000 240000.00| CONTAINMENT AND DISPOSAL OF SPENT | | | MATERIAL | | | SECTION TOTALS | $ 745,000.00| $ 754,325.00| ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 745,000.00| $ 754,325.00| ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 010 -1 VENDOR RANKING CALL ORDER : 010 CONTRACT ID : 9507405 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 CONTRACT DESCRIPTION : NEDS BRANCH BRIDGE PROJECT(S) : S330-0052/04-000.01 00 LOCATION: GUYANDOTTE R, MP 0.00-0.09 0 -------------------------------------------------------------------------------------------------------------------------- TOTAL % OVER RANK VENDOR NO./NAME BID LOW BID -------------------------------------------------------------------------------------------------------------------------- 1 61-0911548 ROBERTS CONSTRUCTION COMPANY $ 740,732.15 100.0000% 2 55-0710073 TEAYS RIVER CONSTRUCTION COMPANY $ 747,327.05 100.8903% 3 55-0622971 KEITH MCCOY, DBA MCCOY CONSTRUCTION COMPANY $ 754,687.65 101.8840% 4 62-1345425 BILCO CONSTRUCTION COMPANY, INC. $ 807,249.00 108.9798% 5 55-0487806 ORDERS CONSTRUCTION COMPANY, INC. $ 823,412.58 111.1619% 6 55-0671461 HOKE BROTHERS CONTRACTING $ 872,021.45 117.7242% 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 010 -2 TABULATION OF BIDS CALL ORDER : 010 CONTRACT ID : 9507405 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(1) 61-0911548 |(2) 55-0710073 |(3) 55-0622971 |ROBERTS CONSTRUCTION COMPANY|TEAYS RIVER CONSTRUCTION COM|MCCOY CONSTRUCTION COMPANY LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 0.260 LS | 29500.00000 29500.00| 60000.00000 60000.00| 18000.00000 18000.00 CLEARING AND GRUBBING | | | 0010 204-01 LUMP| 50000.00000 50000.00| 15000.00000 15000.00| 30000.00000 30000.00 MOBILIZATION | | | 0015 207-01 680.000 M3 | 21.00000 14280.00| 25.00000 17000.00| 12.00000 8160.00 UNCLASSIFIED EXCAVATION | | | 0020 207-02 244.000 M3 | 75.00000 18300.00| 60.00000 14640.00| 45.00000 10980.00 SUBGRADE | | | 0025 207-34 1583.000 M2 | 3.00000 4749.00| 1.00000 1583.00| 2.00000 3166.00 FABRIC FOR SEPARATION | | | 0027 211-01 1307.000 M3 | 20.00000 26140.00| 15.00000 19605.00| 12.00000 15684.00 UNCLASSIFIED BORROW EXCAVATION | | | 0030 307-01 128.100 M3 | 86.00000 11016.60| 85.00000 10888.50| 79.00000 10119.90 CLASS I AGGREGATE BASE COURSE | | | 0035 409-02 1350.000 L | 0.45000 607.50| 0.40000 540.00| 0.44000 594.00 BITUMINOUS MATERIAL PRIME | | | 0037 502-01300 76.000 M2 | 150.00000 11400.00| 235.00000 17860.00| 180.00000 13680.00 PORTLAND CEMENT CONCRETE APPRACH SLAB | | | 300MM | | | 0039 607-011 26.670 M | 155.00000 4133.85| 150.00000 4000.50| 145.00000 3867.15 TYPE 1 GUARDRAIL, CLASS I | | | 0040 607-012 26.670 M | 140.00000 3733.80| 150.00000 4000.50| 130.00000 3467.10 TYPE 1 GUARDRAIL CLASS II | | | 0045 636-11 4230.000 UN | 1.20000 5076.00| 0.01000 42.30| 1.30000 5499.00 TRAFFIC CONTROL DEVICE | | | 0050 636-12 2.000 EA | 340.00000 680.00| 300.00000 600.00| 300.00000 600.00 CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0055 636-13 50.000 EA | 11.00000 550.00| 3.00000 150.00| 10.00000 500.00 CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0060 636-14 600.000 HR | 40.00000 24000.00| 0.01000 6.00| 32.00000 19200.00 FLAGGER | | | 0065 636-17 40.000 M | 152.00000 6080.00| 50.00000 2000.00| 110.00000 4400.00 TEMPORARY CONCRETE BARRIERS | | | 0070 636-25A 800.000 DA | 1.20000 960.00| 0.50000 400.00| 1.10000 880.00 WARNING LIGHTS TYPE A | | | 0075 636-25B 1000.000 DA | 2.00000 2000.00| 1.00000 1000.00| 1.85000 1850.00 WARNING LIGHTS TYPE B | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 010 -3 TABULATION OF BIDS CALL ORDER : 010 CONTRACT ID : 9507405 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(1) 61-0911548 |(2) 55-0710073 |(3) 55-0622971 |ROBERTS CONSTRUCTION COMPANY|TEAYS RIVER CONSTRUCTION COM|MCCOY CONSTRUCTION COMPANY LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0080 638-02 13.000 EA | 75.00000 975.00| 25.00000 325.00| 100.00000 1300.00 RIGHT OF WAY MARKERS | | | 0085 639-01 LUMP| 4500.00000 4500.00| 3000.00000 3000.00| 5000.00000 5000.00 CONSTRUCTION LAYOUT STAKES | | | 0087 640-01 LUMP| 8000.00000 8000.00| 8000.00000 8000.00| 15000.00000 15000.00 STANDARD FIELD OFFICE AND STORAGE | | | BUILDING | | | 0088 640-03 LUMP| 2200.00000 2200.00| 500.00000 500.00| 1500.00000 1500.00 BUILDING EQUIPMENT | | | 0090 642-14 LUMP| 3000.00000 3000.00| 500.00000 500.00| 4000.00000 4000.00 TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 0095 308-01SG AA1 210.100 MGR | 37.00000 7773.70| 40.00000 8404.00| 35.00000 7353.50 CLASS I AGGREGATE BASE COURSE, | | | STONE/GRAVEL | | | 0100 308-01S AA2 191.000 MGR | | | CLASS I AGGREGATE BASE COURSE, SLAG | | | 0105 401-1(1)SG BB1 122.600 MGR | 91.00000 11156.60| 100.00000 12260.00| 85.00000 10421.00 HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0110 401-1(1)S BB2 111.500 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0115 401-2(1)SG CC1 34.100 MGR | 100.00000 3410.00| 100.00000 3410.00| 94.00000 3205.40 HOT-MIX ASPHALT WEARING COURSE, STONE | | | OR GRAVEL | | | 0120 401-2(1)S CC2 31.000 MGR | | | HOT-MIX ASPHALT WEARING COURSE, SLAG | | | SECTION TOTALS | $ 254,222.05| $ 205,714.80| $ 198,427.05 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 BRIDGE | | | 0125 203-01 LUMP| 10000.00000 10000.00| 25000.00000 25000.00| 25000.00000 25000.00 DISMANTLING STRUCTURES | | | 0130 211-02 382.000 M3 | 52.00000 19864.00| 35.00000 13370.00| 70.00000 26740.00 ROCK BORROW EXCAVATION | | | 0135 212-01 158.000 M3 | 26.00000 4108.00| 10.00000 1580.00| 50.00000 7900.00 STRUCTURE EXCAVATION | | | 0140 212-02 100.000 M3 | 26.00000 2600.00| 160.00000 16000.00| 300.00000 30000.00 WET EXCAVATION | | | 0145 212-05 64.000 M3 | 64.00000 4096.00| 130.00000 8320.00| 75.00000 4800.00 SELECT MATERIAL FOR BACKFILLING | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 010 -4 TABULATION OF BIDS CALL ORDER : 010 CONTRACT ID : 9507405 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(1) 61-0911548 |(2) 55-0710073 |(3) 55-0622971 |ROBERTS CONSTRUCTION COMPANY|TEAYS RIVER CONSTRUCTION COM|MCCOY CONSTRUCTION COMPANY LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0150 601-02 137.000 M3 | 625.00000 85625.00| 600.00000 82200.00| 700.00000 95900.00 CLASS B CONCRETE | | | 0155 601-03 209.000 M3 | 700.00000 146300.00| 800.00000 167200.00| 775.00000 161975.00 CLASS K CONCRETE | | | 0160 602-01 7952.000 KG | 1.35000 10735.20| 2.00000 15904.00| 2.20000 17494.40 REIN STEEL BARS | | | 0165 602-02 31507.000 KG | 1.70000 53561.90| 1.75000 55137.25| 1.60000 50411.20 EPOXY COATED REINFORCING BARS | | | 0170 603-18(1372) 268.000 M | 465.00000 124620.00| 450.00000 120600.00| 420.00000 112560.00 PRESTRESSED CONCRETE I BEAMS 1372MM | | | 0175 616-05H310079 66.000 M | 300.00000 19800.00| 550.00000 36300.00| 280.00000 18480.00 STEEL BEARING PILES, HP 310X79, | | | PRE-DRILLED AND DRIVEN | | | 0180 639-01 LUMP| 5200.00000 5200.00| 1.00000 1.00| 5000.00000 5000.00 CONSTRUCTION LAYOUT STAKES | | | SECTION TOTALS | $ 486,510.10| $ 541,612.25| $ 556,260.60 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 740,732.15| $ 747,327.05| $ 754,687.65 ==================================================================================================================================== 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 010 -5 TABULATION OF BIDS CALL ORDER : 010 CONTRACT ID : 9507405 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(4) 62-1345425 |(5) 55-0487806 |(6) 55-0671461 |BILCO CONSTRUCTION COMPANY, |ORDERS CONSTRUCTION COMPANY,|HOKE BROTHERS CONTRACTING LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0001 ROADWAY | | | 0005 201-01 0.260 LS | 6000.00000 6000.00| 55000.00000 55000.00| 25000.00000 25000.00 CLEARING AND GRUBBING | | | 0010 204-01 LUMP| 28000.00000 28000.00| 27000.00000 27000.00| 27000.00000 27000.00 MOBILIZATION | | | 0015 207-01 680.000 M3 | 14.00000 9520.00| 18.50000 12580.00| 0.01000 6.80 UNCLASSIFIED EXCAVATION | | | 0020 207-02 244.000 M3 | 52.00000 12688.00| 72.00000 17568.00| 40.00000 9760.00 SUBGRADE | | | 0025 207-34 1583.000 M2 | 1.50000 2374.50| 1.20000 1899.60| 2.00000 3166.00 FABRIC FOR SEPARATION | | | 0027 211-01 1307.000 M3 | 15.50000 20258.50| 17.00000 22219.00| 12.00000 15684.00 UNCLASSIFIED BORROW EXCAVATION | | | 0030 307-01 128.100 M3 | 52.00000 6661.20| 72.00000 9223.20| 40.00000 5124.00 CLASS I AGGREGATE BASE COURSE | | | 0035 409-02 1350.000 L | 0.50000 675.00| 0.44000 594.00| 0.45000 607.50 BITUMINOUS MATERIAL PRIME | | | 0037 502-01300 76.000 M2 | 150.00000 11400.00| 190.00000 14440.00| 160.00000 12160.00 PORTLAND CEMENT CONCRETE APPRACH SLAB | | | 300MM | | | 0039 607-011 26.670 M | 154.00000 4107.18| 154.00000 4107.18| 155.00000 4133.85 TYPE 1 GUARDRAIL, CLASS I | | | 0040 607-012 26.670 M | 137.50000 3667.12| 137.50000 3667.13| 140.00000 3733.80 TYPE 1 GUARDRAIL CLASS II | | | 0045 636-11 4230.000 UN | 1.00000 4230.00| 1.25000 5287.50| 2.00000 8460.00 TRAFFIC CONTROL DEVICE | | | 0050 636-12 2.000 EA | 0.40000 0.80| 330.00000 660.00| 0.01000 0.02 CLEANING OF PROJECT TRAFFIC CONTROL | | | DEVICE | | | 0055 636-13 50.000 EA | 0.02000 1.00| 3.30000 165.00| 0.01000 0.50 CLEANING OF INDIVIDUAL TRAFFIC CONTROL | | | DEVICE | | | 0060 636-14 600.000 HR | 33.00000 19800.00| 39.00000 23400.00| 0.01000 6.00 FLAGGER | | | 0065 636-17 40.000 M | 50.00000 2000.00| 59.00000 2360.00| 220.00000 8800.00 TEMPORARY CONCRETE BARRIERS | | | 0070 636-25A 800.000 DA | 1.00000 800.00| 0.54000 432.00| 0.50000 400.00 WARNING LIGHTS TYPE A | | | 0075 636-25B 1000.000 DA | 2.50000 2500.00| 1.75000 1750.00| 3.00000 3000.00 WARNING LIGHTS TYPE B | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 010 -6 TABULATION OF BIDS CALL ORDER : 010 CONTRACT ID : 9507405 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(4) 62-1345425 |(5) 55-0487806 |(6) 55-0671461 |BILCO CONSTRUCTION COMPANY, |ORDERS CONSTRUCTION COMPANY,|HOKE BROTHERS CONTRACTING LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0080 638-02 13.000 EA | 125.00000 1625.00| 55.00000 715.00| 90.00000 1170.00 RIGHT OF WAY MARKERS | | | 0085 639-01 LUMP| 3000.00000 3000.00| 5700.00000 5700.00| 16000.00000 16000.00 CONSTRUCTION LAYOUT STAKES | | | 0087 640-01 LUMP| 11000.00000 11000.00| 9800.00000 9800.00| 18000.00000 18000.00 STANDARD FIELD OFFICE AND STORAGE | | | BUILDING | | | 0088 640-03 LUMP| 2000.00000 2000.00| 1000.00000 1000.00| 8000.00000 8000.00 BUILDING EQUIPMENT | | | 0090 642-14 LUMP| 1500.50000 1500.50| 2500.00000 2500.00| 2500.00000 2500.00 TEMPORARY POLLUTION CONTROL BRIDGE | | | PROJECT | | | 0095 308-01SG AA1 210.100 MGR | 25.00000 5252.50| 31.00000 6513.10| 25.00000 5252.50 CLASS I AGGREGATE BASE COURSE, | | | STONE/GRAVEL | | | 0100 308-01S AA2 191.000 MGR | | | CLASS I AGGREGATE BASE COURSE, SLAG | | | 0105 401-1(1)SG BB1 122.600 MGR | 90.20000 11058.52| 90.00000 11034.00| 91.00000 11156.60 HOT-MIX ASPHALT BASE COURSE, STONE OR | | | GRAVEL | | | 0110 401-1(1)S BB2 111.500 MGR | | | HOT-MIX ASPHALT BASE COUSRE, SLAG | | | 0115 401-2(1)SG CC1 34.100 MGR | 100.00000 3410.00| 99.00000 3375.90| HOT-MIX ASPHALT WEARING COURSE, STONE | | | OR GRAVEL | | | 0120 401-2(1)S CC2 31.000 MGR | | | 100.00000 3100.00 HOT-MIX ASPHALT WEARING COURSE, SLAG | | | SECTION TOTALS | $ 173,529.82| $ 242,990.61| $ 192,221.57 ------------------------------------------+----------------------------+----------------------------+------------------------------- SECTION 0002 BRIDGE | | | 0125 203-01 LUMP| 104500.00000 104500.00| 44300.00000 44300.00| 35000.00000 35000.00 DISMANTLING STRUCTURES | | | 0130 211-02 382.000 M3 | 34.00000 12988.00| 52.60000 20093.20| 45.00000 17190.00 ROCK BORROW EXCAVATION | | | 0135 212-01 158.000 M3 | 45.00000 7110.00| 0.01000 1.58| 0.01000 1.58 STRUCTURE EXCAVATION | | | 0140 212-02 100.000 M3 | 85.00000 8500.00| 300.00000 30000.00| 250.00000 25000.00 WET EXCAVATION | | | 0145 212-05 64.000 M3 | 85.00000 5440.00| 128.00000 8192.00| 100.00000 6400.00 SELECT MATERIAL FOR BACKFILLING | | | 1 WEST VIRGINIA DEPARTMENT OF TRANSPORTATION Division of Highways DATE : 03/12/98 PAGE : 010 -7 TABULATION OF BIDS CALL ORDER : 010 CONTRACT ID : 9507405 COUNTIES : MINGO LETTING DATE : 02/24/98 10:00 A.M. DISTRICT : 02 SET-ASIDE : ==================================================================================================================================== |(4) 62-1345425 |(5) 55-0487806 |(6) 55-0671461 |BILCO CONSTRUCTION COMPANY, |ORDERS CONSTRUCTION COMPANY,|HOKE BROTHERS CONTRACTING LINE NO / ITEM CODE / ALT | | | ITEM DESCRIPTION QUANTITY | UNIT PRICE AMOUNT| UNIT PRICE AMOUNT| UNIT PRICE AMOUNT ------------------------------------------+----------------------------+----------------------------+------------------------------- 0150 601-02 137.000 M3 | 678.00000 92886.00| 760.00000 104120.00| 730.00000 100010.00 CLASS B CONCRETE | | | 0155 601-03 209.000 M3 | 863.00000 180367.00| 760.00000 158840.00| 860.00000 179740.00 CLASS K CONCRETE | | | 0160 602-01 7952.000 KG | 1.50000 11928.00| 1.35000 10735.20| 1.80000 14313.60 REIN STEEL BARS | | | 0165 602-02 31507.000 KG | 1.75000 55137.25| 1.57000 49465.99| 2.10000 66164.70 EPOXY COATED REINFORCING BARS | | | 0170 603-18(1372) 268.000 M | 520.00000 139360.00| 418.00000 112024.00| 710.00000 190280.00 PRESTRESSED CONCRETE I BEAMS 1372MM | | | 0175 616-05H310079 66.000 M | 197.00000 13002.00| 525.00000 34650.00| 450.00000 29700.00 STEEL BEARING PILES, HP 310X79, | | | PRE-DRILLED AND DRIVEN | | | 0180 639-01 LUMP| 2500.93000 2500.93| 8000.00000 8000.00| 16000.00000 16000.00 CONSTRUCTION LAYOUT STAKES | | | SECTION TOTALS | $ 633,719.18| $ 580,421.97| $ 679,799.88 ------------------------------------------+----------------------------+----------------------------+------------------------------- CONTRACT TOTALS | $ 807,249.00| $ 823,412.58| $ 872,021.45 ====================================================================================================================================