Section 108.7.1 - Liquidated Damages Table
TABLE 108.7.1 SCHEDULE OF LIQUIDATED DAMAGES
|
ORIGINAL CONTRACT AMOUNT
|
DAILY CHARGE
|
|
From More Than
|
To And Including
|
Per Calendar Day
|
|
|
|
|
|
$ 0
|
$ 25,000
|
$ 40
|
|
$ 25,000
|
$ 100,000
|
$ 70
|
|
$ 100,000
|
$ 500,000
|
$ 150
|
|
$ 500,000
|
$ 1,000,000
|
$ 310
|
|
$ 1,000,000
|
$ 2,000,000
|
$ 570
|
|
$ 2,000,000
|
$ 5,000,000
|
$ 910
|
|
$ 5,000,000
|
$ 10,000,000
|
$ 1410
|
|
$ 10,000,000
|
----------------
|
$ 3280
|