District 5 Work Zones

District 5 RoadsRoad work projects within District 5. Only those work activities that are expected to affect traffic are listed.

On this Page:
  • Interstate Work Zones
  • US Route Work Zones
  • County Work Zones

    • Berkeley
    • Grant
    • Hampshire
    • Hardy
    • Jefferson
    • Mineral
    • Morgan

  

US Route Work Zones

Affected
Route
Activity
Start Date
End Date
Type of Project

US 522
Resurfacing w/base failure repairs, SHL widening and rumble strips
09/09/2014
10/31/2014
Construction Project
Notes: Resurfacing project with base repair, paved shoulders, and rumble strips. Project begins at the VA state line at MP 0.00 and ends at Jct. CR 28. Project Length - 3.67 Miles. the rumble strips will be installed from the VA line to the MD line on US 522.

WV Routes

All Routes with centerline and/or edgeline
Roadway Striping
06/30/2014
05/15/2015
Construction Project
Notes: Recall job orders to paint various centrline, edgeline, and laneline in Ditrict Five that is not covered under the current District-wide striping contract.

WV 29
Resurfacing w/Shoulder Widening & Base Repair
08/25/2014
09/30/2014
Construction Project
Notes: Resurfacing project with base repair and paved shoulders. Project begins 0.45 miles north of CR 11/5 at MP 5.52 and ends 0.84 miles North of CR 11/4. Project Length - 3.00 Miles.

WV 259
Resurfacing w/Shoulder Widening & Base Repair
07/29/2014
10/17/2014
Construction Project
Notes: Resurfacing project with base repair and paved shoulders. Project begins at 0..05 miles south of CR 259/6 at MP 1.98 and ends 0.77 miles south of CR 18. Project length - 2 miles.

WV 46
Microsurfacing with Edge/Base Repairs
08/06/2014
09/30/2014
Construction Project
Notes: Microsurfacing project with edge/base repairs. Project begins 0.21 miles west of CR 11 at MP 29.33 and ends at Jct. of WV 28. Project Length - 6.21.

WV 9
Resurfacing w/sholder widening, base repair & milling
05/19/2014
10/17/2014
Construction Project
Notes: Resurfacing project with base repair and paved shoulders. Project begins at Jct. CR 9/11 at MP 23.12 and ends at Jct. US 522. Project Length - 2.18 Miles.

County Work Zones

GRANT

Affected
Route
Activity
Start Date
End Date
Type of Project

CR 5
Resurfacing w/shoulder widening and base repair
09/15/2014
09/30/2014
Construction Project
Notes: Resurfacing project with base repair and paved shoulders. Project begins 0.36 miles south of CR 2 at MP 11.10 and ends 0.33 miles north of CR 5/2. Project Length - 1.56 Miles.