West Virginia Parkways Authority

Weekly Construction Schedule

Weekly Work Schedule - 04/20/2015 - 04/24/2015
 
Bridge Repair & Inspections

Work Description
Work Location
Mon
Tues
Wed
Thurs
Fri
Bridge Prep/Paint Right Shoulder Closure 51.4 NB/48 SB
 
 
 
 
 
Bridge Prep/Paint MP 48.5 to 48 S/B Truck Lane
 
 
 
 
 
Bridge Prep/Paint Right Shoulder Closure 51.4 NB/48 SB
 
 
 
 
 
Bridge Prep/Paint Right Shoulder Closure 51.4 & 39.4 NB/48 & 47 SB
 
 
 
 
 
Stud Retrofit Bridge 3038-N (Permanent Closure) MP 46 to 46.9 N/B Left Lane
 
 
 
 
 


Concrete Repair
Work Description
Work Location
Mon
Tues
Wed
Thurs
Fri
Concrete Repair (6PM to 6AM) MP 32.5 to 32 S/B Left 2 Lanes
 
 
 
 
 
Concrete Repair (6PM to 6AM) Bar. A NB MP 29.5 to 30.1 N/B Right Lane
 
 
 
 
 
Concrete Repair (6PM to 6AM) Bar. A SB MP 31 to 30 S/B Right Lane
 
 
 
 
 


Ditch Line/Culvert Cleaning & Repair
Work Description
Work Location
Mon
Tues
Wed
Thurs
Fri
Gutter Repair (6AM to 6PM) 85 SB-Right Shoulder Closure
 
 
 
 
 
Gutter Repair(6AM to 6PM) 85 SB-Right Shoulder Closure
 
 
 
 
 
Shoulder Prep (6AM to 6PM) MP 36 to 37 N/B Right Lane
 
 
 
 
 
Shoulder Prep (6AM to 6PM) MP 35 to 36 N/B Right Lane
 
 
 
 
 


Other
Work Description
Work Location
Mon
Tues
Wed
Thurs
Fri
Line Painting (10AM to 6PM) MP 9 to 30 N/B Left Lane
 
 
 
 
 
Line Painting (10AM to 6PM) MP 30 to 50 N/B Left Lane
 
 
 
 
 
Line Painting (10AM to 6PM) MP 80 to 96 N/B Left Lane
 
 
 
 
 
Line Painting (10AM to 6PM) MP 32 to 9 S/B Left Lane
 
 
 
 
 
Line Painting (10AM to 6PM) MP 50 to 80 N/B Left Lane
 
 
 
 
 
Subgrade Stabilization (6PM to 6AM) MP 86.5 to 86 S/B Right Lane
 
 
 
 
 
Subgrade Stabilization (6PM to 6AM) MP 86.5 to 85.5 S/B Right Lane
 
 
 
 
 